2331 S PORTLAND ST 90007

Certificate Information: 2331 S PORTLAND ST 90007

Application / Permit
21016-10000-12060
Plan Check / Job No.
B21LA08908
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan:Soft-Story seismic retrofit per LABC Chapter 93: Verify work done under ADU Permit#21016-100000-13661 using wood shear walls meets the minimum requirement of soft story ordinance.Certificate of Compliance for soft story shall not be issued till Certificate of Occupancy for ADU permit is obtained
Permit Issued
Issued on 4/4/2023
Issuing Office
Current Status
Issued on 4/4/2023

Permit Application Status History

Submitted 5/13/2021 APPLICANT
Assigned to Plan Check Engineer 6/10/2021 VARAND SARKISIAN
Corrections Issued 6/14/2021 VARAND SARKISIAN
Quality Review Completed 6/17/2021 HANS SANTIAGO
Applicant returned to address corrections 10/25/2021 VARAND SARKISIAN
Applicant returned to address corrections 5/6/2022 VARAND SARKISIAN
Applicant returned to address corrections 6/17/2022 VARAND SARKISIAN
Plan Check Approved 7/6/2022 VARAND SARKISIAN
Issued 4/4/2023 APPLICANT

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 10/5/2021 LAMBERT GIESSINGER
Historic monument Cleared 10/5/2021 LAMBERT GIESSINGER
HPOZ Cleared 10/6/2021 KATIE DEBIASE
DAS Clearance Cleared 5/17/2022 ANDREW SANTIAGO
Tenant Habitability Plan Cleared 7/20/2022 RICARDO BOHORQUEZ

Contact Information

Contractor Best Bath & Kitchen Construction; Lic. No.: 1002039-B       ,
Engineer Zhang,, Yao; Lic. No.: C74572 538 ROCCO CIRCLE      CORONA, CA 92882

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 7/18/2023 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 7/18/2023 Conditional Approval DARRYL ARNOLD
Floor/Roof Diaphrgm/Shear Wall 8/16/2023 Approved DARRYL ARNOLD
Wood Frame 8/16/2023 Conditional Approval DARRYL ARNOLD
Interior/Exterior Lathing 8/29/2023 Approved DARRYL ARNOLD
Final 1/5/2024 Not Ready for Inspection JACOB MYERS
METHANE-Final 1/5/2024 Approved JACOB MYERS
SGSOV-Seismic Gas S/O Valve 1/5/2024 SGSOV No Gas JACOB MYERS
Smoke Detectors 1/5/2024 Not Ready for Inspection JACOB MYERS
Final 1/12/2024 Not Ready for Inspection DARRYL ARNOLD
Smoke Detectors 1/12/2024 Not Ready for Inspection DARRYL ARNOLD
Final 1/18/2024 Not Ready for Inspection DARRYL ARNOLD
Smoke Detectors 1/18/2024 Conditional Approval DARRYL ARNOLD