6107 N TUJUNGA AVE 91606

Certificate Information: 6107 N TUJUNGA AVE 91606

Application / Permit
21016-10000-12014
Plan Check / Job No.
B21LA08880
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
Eplan: Soft-Story seismic retrofit per LABC Chapter 93: Install 1 Special Steel Cantilever Column
Permit Issued
Issued on 7/7/2021
Issuing Office
Current Status
CofC Issued on 12/23/2021

Permit Application Status History

Submitted 5/10/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 HANS SANTIAGO
Corrections Issued 5/24/2021 HANS SANTIAGO
Quality Review Completed 5/26/2021 SAI KHUM
Plan Check Approved 6/9/2021 ANDREW SANTIAGO
Issued 7/7/2021 APPLICANT
OK for CofC 10/25/2021 KENNETH ROBERTS
CofC Issued 12/23/2021 KENNETH ROBERTS

Permit Application Clearance Information

Tenant Habitability Plan Cleared 7/7/2021 MICHAEL SOTO

Contact Information

Contractor Optimum Seismic Inc; Lic. No.: 1012702-B 5508 S SANTA FE AVENUE      VERNON, CA 90058
Engineer Mirmohammadsadeghi,, Kamaleddin; Lic. No.: C53468 1377 S BEVERLY GLEN BLVD 308      LOS ANGELES, CA 90024

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 7/12/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Steel/Welding 7/15/2021 Corrections Issued JOE VELASQUEZ
Deputy Drilled-In Anchors 7/16/2021 No Access for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 7/16/2021 No Access for Inspection JOE VELASQUEZ
Deputy Drilled-In Anchors 7/21/2021 No Access for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 7/21/2021 No Access for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 7/27/2021 Corrections Issued JOE VELASQUEZ
Structural Steel Frame 7/27/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/27/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 7/29/2021 Not Ready for Inspection JOE VELASQUEZ
Structural Steel Frame 7/29/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 7/29/2021 Not Ready for Inspection JOE VELASQUEZ
Footing/Foundation/Slab 8/5/2021 Approved JOE VELASQUEZ
Structural Steel Frame 8/5/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/5/2021 Not Ready for Inspection JOE VELASQUEZ
Deputy Reinf. Concrete 8/6/2021 Approved JOE VELASQUEZ
Insulation 8/11/2021 Not Ready for Inspection JOE VELASQUEZ
Wood Frame 8/11/2021 Corrections Issued JOE VELASQUEZ
Insulation 8/13/2021 Approved JOE VELASQUEZ
Wood Frame 8/13/2021 Approved JOE VELASQUEZ
Drywall Nailing 8/26/2021 Approved JOE VELASQUEZ
Final 10/22/2021 Partial Inspection KENNETH ROBERTS
SGSOV-Seismic Gas S/O Valve 10/22/2021 SGSOV Approved KENNETH ROBERTS
Smoke Detectors 10/22/2021 Approved KENNETH ROBERTS
Final 10/25/2021 OK for CofC KENNETH ROBERTS