2756 1/2 W 15TH ST 90006

Certificate Information: 2756 1/2 W 15TH ST 90006

Application / Permit
21016-10000-11995
Plan Check / Job No.
B21LA08875
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) RECREATION ROOM AND VOID SPACE TO ADU PER GCS 65852.2 & 65852.22
Permit Issued
Issued on 8/13/2021
Issuing Office
Current Status
CofO Issued on 10/27/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/14/2021 HERNAN ARREOLA
Corrections Issued 5/14/2021 HERNAN ARREOLA
Plan Check Approved 6/24/2021 KEVIN MORALES
Issued 8/13/2021 APPLICANT
CofO in Progress 6/21/2022 STUART CHAPMAN
CofO Issued 10/27/2022 DEROLD HAUFF
Permit Finaled 10/27/2022 DEROLD HAUFF

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 6/9/2021 JEREMY CHOK
Sewer availability Cleared 6/9/2021 JEREMY CHOK
Address approval Cleared 6/10/2021 JEREMY CHOK
HPOZ Cleared 6/22/2021 DEEPEAKA DHALIWAL

Contact Information

Contractor Affordable Building Solutions Inc; Lic. No.: 1068574-B 8885 SANDALWOOD CT      RANCHO CUCAMONGA, CA 91730

Inspector Information

WILLIAM SIERRA, (213) 202-3122 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/19/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 8/25/2021 Corrections Issued KATHRYN BUTTERWORTH
PLUMBING-Rough 8/25/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 9/7/2021 Not Ready for Inspection FREDDIE RIVERA
Footing/Foundation/Slab 9/7/2021 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 9/7/2021 Corrections Issued FREDDIE RIVERA
Wood Frame 9/7/2021 Not Ready for Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 9/28/2021 Partial Approval ROBERT VORHIS
Excavation/Setback/Form/Re-Bar 10/8/2021 Partial Approval HORACE FULTZ
Footing/Foundation/Slab 10/19/2021 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/28/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Rough 10/28/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Footing/Foundation/Slab 10/28/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
HVAC-Rough 10/28/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Sewer 10/28/2021 Partial Approval KATHRYN BUTTERWORTH
ELECTRICAL-Rough 11/30/2021 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Rough 11/30/2021 Partial Approval KATHRYN BUTTERWORTH
PLUMBING-Rough 11/30/2021 Partial Approval KATHRYN BUTTERWORTH
Shower Pan 12/3/2021 Approved KATHRYN BUTTERWORTH
Insulation 12/8/2021 Not Ready for Inspection KATHRYN BUTTERWORTH
Rough-Elec/Plmb/HVAC 12/8/2021 Approved KATHRYN BUTTERWORTH
BUILDING-Rough-Frame 12/21/2021 Approved KATHRYN BUTTERWORTH
Insulation 12/21/2021 Approved KATHRYN BUTTERWORTH
ELECTRICAL-Final 6/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Final 6/2/2022 Corrections Issued KATHRYN BUTTERWORTH
HVAC-Final 6/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
PLUMBING-Final 6/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
SGSOV-Seismic Gas S/O Valve 6/2/2022 SGSOV Not Ready KATHRYN BUTTERWORTH
Service/Power Release 6/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
Smoke Detectors 6/2/2022 Not Ready for Inspection KATHRYN BUTTERWORTH
ELECTRICAL-Final 6/20/2022 Approved STUART CHAPMAN
Final 6/20/2022 OK to Issue CofO STUART CHAPMAN
HVAC-Final 6/20/2022 Approved STUART CHAPMAN
PLUMBING-Final 6/20/2022 Approved STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 6/20/2022 SGSOV Approved STUART CHAPMAN
Service/Power Release 6/20/2022 Approved STUART CHAPMAN
Smoke Detectors 6/20/2022 Approved STUART CHAPMAN