11262-11264 W ARMINTA ST 91352
Certificate Information: 11262-11264 W ARMINTA ST 91352
- Application / Permit
- 21016-10000-11738
- Plan Check / Job No.
- B21LA08656
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISITNG ATTACHED GARAGE TO AN ADU.
- Permit Issued
- Issued on 5/26/2021
- Issuing Office
- Current Status
- CofO Issued on 5/14/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/6/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/11/2021 | JOE VO |
| Corrections Issued | 5/11/2021 | JOE VO |
| Plan Check Approved | 5/20/2021 | JOE VO |
| Issued | 5/26/2021 | APPLICANT |
| CofO in Progress | 3/2/2022 | CHRISTOPHER DELLEFIELD |
| CofO Issued | 5/14/2022 | MICHAEL SMITH |
| Permit Finaled | 5/14/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/12/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2021 | GABRIEL ROBLES |
| Hold | Cleared | 7/29/2021 | Yasaman Shayesteh |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| MATTHEW NELSON, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/30/2021 | Conditional Approval | ALAN MORELOS |
| Footing/Foundation/Slab | 8/2/2021 | Corrections Issued | JOHN HAYES |
| Sewer | 8/2/2021 | Not Ready for Inspection | JOHN HAYES |
| Footing/Foundation/Slab | 9/9/2021 | Approved | JOHN HAYES |
| Sewer | 9/9/2021 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 10/4/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 10/4/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 10/4/2021 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Wood Frame | 10/4/2021 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Interior/Exterior Lathing | 1/13/2022 | Approved | DEANDRE HOFFMAN |
| BUILDING-Rough-Frame | 2/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| ELECTRICAL-Final | 2/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 2/25/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| HVAC-Final | 2/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Final | 2/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| SGSOV-Seismic Gas S/O Valve | 2/25/2022 | SGSOV Not Required | CHRISTOPHER DELLEFIELD |
| Smoke Detectors | 2/25/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Final | 3/2/2022 | OK to Issue CofO | CHRISTOPHER DELLEFIELD |