10285 S POST WAY 90045
Certificate Information: 10285 S POST WAY 90045
- Application / Permit
- 21016-10000-11715
- Plan Check / Job No.
- B21LA08629
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- ***LAX*** INTERIOR AND EXTERIOR ALTERATION OF EXISTING OFFICE BUILDING TO TELECOMMUNICATIONS FACILITY. INTERIOR ALTERATION INCLUDES THE FOLLOWING: INTERIOR DEMOLITOIN OF ATRIUM/LOBBY 'MAIN' FIRST FLOOR, DEMO 'SUB-1' FIRST FLOOR, AND DEMO 'SUB-2' SECOND FLOOR TO CONVERT TO EQUIOPMENT USE AREAS. FOR EXTERIOR ALTERATION, NEW STEEL PLATFORM AND EQUIPMENT ANCHORAGES AT ROOF 'MECH 2'.
- Permit Issued
- Issued on 12/10/2021
- Issuing Office
- Current Status
- Issued on 12/10/2021
Permit Application Status History
| Submitted | 5/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | EDUARDO RODRIGUEZ |
| Corrections Issued | 6/25/2021 | EDUARDO RODRIGUEZ |
| Quality Review Completed | 6/28/2021 | LIPING TENG |
| Building Plans Picked Up | 6/29/2021 | APPLICANT |
| Applicant returned to address corrections | 10/4/2021 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 10/7/2021 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 10/14/2021 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/4/2021 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/8/2021 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/9/2021 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/16/2021 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 11/18/2021 | EDUARDO RODRIGUEZ |
| Applicant returned to address corrections | 12/7/2021 | EDUARDO RODRIGUEZ |
| Plan Check Approved | 12/9/2021 | EDUARDO RODRIGUEZ |
| Issued | 12/10/2021 | APPLICANT |
Permit Application Clearance Information
| DAS Clearance | Cleared | 6/4/2021 | SHINE LIN |
| Project Permit | Cleared | 7/20/2021 | VINITA WASKOW |
| City owned building/parcel | Cleared | 8/6/2021 | EDUARDO RODRIGUEZ |
| Plan Approval | Cleared | 8/6/2021 | DAVID URITA |
| Specific Plan | Cleared | 8/20/2021 | EDDIE GUERRERO |
| Eng Process Fee Ord 176,300 | Cleared | 8/24/2021 | NIKTA MOUSAVI |
| Sewer availability | Cleared | 9/9/2021 | NIKTA MOUSAVI |
| Hydrant and Access approval | Cleared | 9/13/2021 | JOHN CONNEALLY |
| Airport buildings | Cleared | 10/4/2021 | ANDREW KO |
| Green Code | Cleared | 10/12/2021 | EDUARDO RODRIGUEZ |
Contact Information
| Contractor | Aztecs Telecom Inc; Lic. No.: 890747-B | 1353 WALKER LN CORONA, CA 92879 |
| Engineer | Donohoe,, Patrick; Lic. No.: L9332 | 819 JOLLEY RD DOYLE, TN 38559 |
| Engineer | Scharlin,, Russell J; Lic. No.: GE751 | 17782 GEORGETOWN LANE HUNTINGTON BEACH, CA 92647 |
| Engineer | Teng,, Albert Rhui-Hong; Lic. No.: C41170 | 2362 MCGAW AVE IRVINE, CA 92614 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 12/20/2021 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 12/21/2021 | Approved | JONATHAN ALLEN |
| Footing/Foundation/Slab | 12/21/2021 | Approved | JONATHAN ALLEN |
| Pre-Inspection | 12/21/2021 | Approved | JONATHAN ALLEN |
| Deputy Reinf. Concrete | 12/22/2021 | Conditional Approval | GRANT WOODS |
| Light Gage Steel Frame | 1/11/2022 | Partial Approval | ALAN NOVAK |
| Deputy Fireproofing | 1/14/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 1/20/2022 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 2/9/2022 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 2/11/2022 | Partial Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 2/16/2022 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 3/3/2022 | Partial Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 3/4/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 3/8/2022 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 3/9/2022 | Partial Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 4/5/2022 | Conditional Approval | ALAN NOVAK |
| Footing/Foundation/Slab | 4/8/2022 | Partial Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 4/13/2022 | Conditional Approval | ALAN NOVAK |
| Light Gage Steel Frame | 5/25/2022 | Partial Approval | ALAN NOVAK |
| Deputy Steel/Welding | 6/28/2022 | Conditional Approval | ALAN NOVAK |
| Drywall Nailing | 7/20/2022 | Approved | ALAN NOVAK |
| Light Gage Steel Frame | 7/20/2022 | Approved | ALAN NOVAK |
| Structural Steel Frame | 7/20/2022 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/24/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 10/14/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 11/1/2022 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 4/13/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 5/11/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 6/2/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 6/28/2023 | Partial Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 7/31/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 8/4/2023 | Approved | ALAN NOVAK |
| Deputy Reinf. Concrete | 9/27/2023 | Conditional Approval | ALAN NOVAK |
| Deputy Reinf. Concrete | 1/18/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 5/24/2024 | Approved | NICK LAROCCA |
| Deputy Reinf. Concrete | 7/17/2024 | Conditional Approval | ALAN NOVAK |
| Deputy Drilled-In Anchors | 7/31/2024 | Conditional Approval | ALAN NOVAK |
| T-Bar Ceiling | 8/30/2024 | Not Ready for Inspection | ALAN NOVAK |
| Deputy Drilled-In Anchors | 5/5/2025 | Approved | NICK LAROCCA |