2335 S CHARITON ST 90034
Certificate Information: 2335 S CHARITON ST 90034
- Application / Permit
- 21016-10000-11624
- Plan Check / Job No.
- B21LA08566
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: 23531 Soft-Story seismic retrofit per LABC Chapter 93: Seismic upgrade of soft-story building by installing simpson steel strong walls and 2 special catilever columns
- Permit Issued
- Issued on 10/4/2021
- Issuing Office
- Current Status
- CofC Issued on 4/1/2022
Permit Application Status History
| Submitted | 5/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | JESSE VIDUYA |
| Corrections Issued | 6/15/2021 | JESSE VIDUYA |
| Quality Review Completed | 6/23/2021 | HANS SANTIAGO |
| Applicant returned to address corrections | 8/11/2021 | JESSE VIDUYA |
| Plan Check Approved | 8/16/2021 | JESSE VIDUYA |
| Issued | 10/4/2021 | APPLICANT |
| OK for CofC | 3/25/2022 | GRANT WOODS |
| CofC Issued | 4/1/2022 | DAVID TSAU |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/24/2021 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Action Construction Company; Lic. No.: 640072-B | 6924 CANBY AVE #112 LOS ANGELES, CA 91355 |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 10/18/2021 | Approved | GRANT WOODS |
| Footing/Foundation/Slab | 11/15/2021 | Conditional Approval | JOHN DODGE |
| Wood Frame | 11/15/2021 | Not Ready for Inspection | JOHN DODGE |
| Deputy Reinf. Concrete | 11/19/2021 | Conditional Approval | JOHN DODGE |
| Structural Steel Frame | 11/23/2021 | Approved | JOHN DODGE |
| Wood Frame | 11/23/2021 | Partial Approval | JOHN DODGE |
| Wood Frame | 12/2/2021 | Not Ready for Inspection | JOHN DODGE |
| Wood Frame | 12/7/2021 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 1/7/2022 | Approved | GRANT WOODS |
| Final | 1/27/2022 | Not Ready for Inspection | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 1/27/2022 | SGSOV Not Ready | PAUL DAVIDSON |
| Smoke Detectors | 1/27/2022 | Approved | PAUL DAVIDSON |
| SGSOV-Seismic Gas S/O Valve | 3/22/2022 | SGSOV Approved | GRANT WOODS |
| Final | 3/25/2022 | OK for CofC | GRANT WOODS |