1020 S FIGUEROA ST 90015
Certificate Information: 1020 S FIGUEROA ST 90015
- Application / Permit
- 21016-10000-11545
- Plan Check / Job No.
- B21LA08498
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (11) Hotel
- Work Description
- eplan: Repair one damaged concrete beam
- Permit Issued
- Issued on 10/6/2021
- Issuing Office
- Current Status
- Permit Finaled on 1/21/2022
Permit Application Status History
| Submitted | 5/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | LARRY LEE |
| Corrections Issued | 5/6/2021 | LARRY LEE |
| Applicant returned to address corrections | 7/30/2021 | LARRY LEE |
| Plan Check Approved | 9/29/2021 | LARRY LEE |
| Issued | 10/6/2021 | APPLICANT |
| Permit Finaled | 1/20/2022 | TIMOTHY BUXTON |
Permit Application Clearance Information
| Redevelopment Project Area | Cleared | 9/23/2021 | GRACIELA ACOSTA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Zhuang,, Wenbin; Lic. No.: NA5236 | , |
Inspector Information
| JEROME BLACKWOOD, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
| REGINA MENDEZ, (213) 213-5353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 11/18/2021 | Conditional Approval | TIMOTHY BUXTON |
| Deputy Reinf. Concrete | 11/18/2021 | Conditional Approval | TIMOTHY BUXTON |
| Reinforced Concrete Frame | 12/17/2021 | Approved | JONATHAN QUACH |
| Deputy Fireproofing | 1/13/2022 | Conditional Approval | TIMOTHY BUXTON |
| Final | 1/20/2022 | Permit Finaled | TIMOTHY BUXTON |
| SGSOV-Seismic Gas S/O Valve | 1/20/2022 | SGSOV Approved | TIMOTHY BUXTON |
| Smoke Detectors | 1/20/2022 | Approved | TIMOTHY BUXTON |