16450 W VENTURA BLVD 91436

Certificate Information: 16450 W VENTURA BLVD 91436

Application / Permit
21016-10000-11438
Plan Check / Job No.
B21LA08419
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
Grocery Market Tenant Improvement INTERIOR AND EXTERIOR Renovation Area of work 4,215 SF
Permit Issued
Issued on 9/27/2021
Issuing Office
Current Status
Permit Finaled on 10/10/2023

Permit Application Status History

Submitted 5/11/2021 APPLICANT
Assigned to Plan Check Engineer 5/27/2021 HERNAN ARREOLA
Corrections Issued 6/1/2021 HERNAN ARREOLA
Quality Review Completed 6/10/2021 JASON HEALEY
Plan Check Approved 9/16/2021 HERNAN ARREOLA
Issued 9/27/2021 APPLICANT
Permit Finaled 9/14/2023 STEVEN LEVITT

Permit Application Clearance Information

Miscellaneous Cleared 7/28/2021 ANACANY HURTADO
Specific Plan Cleared 8/25/2021 CORREY KITCHENS
Food establishment approval Cleared 9/16/2021 LACDHS APPROVED

Contact Information

Architect Kelley,, Kevin E; Lic. No.: NA27298       ,
Contractor Kirkley Corporation Inc; Lic. No.: 408026-B P O BOX 7268      REDLANDS, CA 92375
Engineer Baroonian,, Armen; Lic. No.: S4227 867 N FAIR OAKS AVE 100      PASADENA, CA 91103

Inspector Information

SEAN GRIFFITH, (818) 374-1102 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 10/6/2021 Partial Inspection DANIEL VARNUM
Pre-Inspection 10/8/2021 Approved ROBERT DAVIS
Pre-Inspection 10/8/2021 Off-Hour Fees Due
Smoke Detectors 10/8/2021 No Result Entered JOE VELASQUEZ
Reinforced Masonry Frame 10/12/2021 Not Ready for Inspection DANNY RODRIGUEZ
Deputy Drilled-In Anchors 10/13/2021 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 10/14/2021 Partial Inspection DANNY RODRIGUEZ
Masonry Wall/Backfill 10/14/2021 Partial Approval DANNY RODRIGUEZ
Deputy Reinf. Masonry 10/15/2021 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 3/3/2022 Partial Approval JEFFREY DURAN
Light Gage Steel Frame 3/16/2022 Partial Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 3/17/2022 Partial Approval CAMERON CHABAN
Excavation/Setback/Form/Re-Bar 3/24/2022 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 3/31/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 4/1/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 4/12/2022 Not Ready for Inspection JEFFREY FULTON
Drywall Nailing 4/13/2022 Partial Inspection CAMERON CHABAN
Light Gage Steel Frame 5/10/2022 Corrections Issued CAMERON CHABAN
Drywall Nailing 5/17/2022 Partial Approval CAMERON CHABAN
Drywall Nailing 5/23/2022 No Access for Inspection DANIEL VARNUM
Drywall Nailing 5/24/2022 Partial Inspection CAMERON CHABAN
Drywall Nailing 6/14/2022 Partial Inspection CAMERON CHABAN
Light Gage Steel Frame 6/24/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 6/30/2022 Conditional Approval CAMERON CHABAN
Light Gage Steel Frame 6/30/2022 Conditional Approval CAMERON CHABAN
Drywall Nailing 7/18/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 7/18/2022 Partial Inspection JEFFREY FULTON
Light Gage Steel Frame 9/20/2022 Conditional Approval BRUCE CAMPBELL
Drywall Nailing 10/5/2022 Approved CAMERON CHABAN
Final 10/27/2022 Not Ready for Inspection ROBERT DAVIS
Green Building Final 10/27/2022 Approved ROBERT DAVIS
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Approved ROBERT DAVIS
Final 9/14/2023 Permit Finaled STEVEN LEVITT
Smoke Detectors 10/10/2023 Approved STEVEN LEVITT