715 1/2 N HOLLAND AVE 90042

Certificate Information: 715 1/2 N HOLLAND AVE 90042

Application / Permit
21016-10000-11434
Plan Check / Job No.
B21LA08412
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT GARAGE AND PLAY ROOM TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
CofO Issued on 5/3/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/4/2021 APPLICANT
Assigned to Plan Check Engineer 5/5/2021 KEVIN MORALES
Corrections Issued 5/5/2021 KEVIN MORALES
Plan Check Approved 5/24/2021 KEVIN MORALES
Issued 6/7/2021 APPLICANT
CofO in Progress 3/23/2022 HAMIK HARTOUNIAN
Permit Finaled 5/3/2022 DEROLD HAUFF
CofO Issued 5/3/2022 DEROLD HAUFF
Permit Finaled 5/3/2022 DEROLD HAUFF

Permit Application Clearance Information

City Hist. Cultural Monument Cleared 5/10/2021 KATIE DEBIASE
HPOZ Cleared 5/10/2021 KATIE DEBIASE
Historic monument Cleared 5/10/2021 KATIE DEBIASE
Miscellaneous Cleared 5/10/2021 KATIE DEBIASE
Miscellaneous Cleared 5/10/2021 KATIE DEBIASE
ZA Case Cleared 5/10/2021 KATIE DEBIASE
Address approval Cleared 5/12/2021 THOMAS LANG
Sewer availability Cleared 5/12/2021 THOMAS LANG
Grading Pre-Inspection Cleared 5/18/2021 KIRK LINKLATER
Eng Process Fee Ord 176,300 Cleared 5/24/2021 THOMAS LANG

Contact Information

Contractor D M General Construction Inc; Lic. No.: 1014961-B 1727 NORTH EL SERENO AVE APT 1      PASADENA, CA 91103
Engineer Chen,, Junfei; Lic. No.: C85841 726 FAMILY TREE      IRVINE, CA 92618

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/3/2021 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 9/7/2021 Conditional Approval HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/14/2021 Corrections Issued HAMIK HARTOUNIAN
ELECTRICAL-Rough 10/14/2021 Corrections Issued HAMIK HARTOUNIAN
Green Building Rough 10/14/2021 Not Ready for Inspection HAMIK HARTOUNIAN
PLUMBING-Rough 10/14/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/14/2021 Partial Approval HAMIK HARTOUNIAN
ELECTRICAL-Rough 12/14/2021 Partial Approval HAMIK HARTOUNIAN
Green Building Rough 12/14/2021 Approved HAMIK HARTOUNIAN
PLUMBING-Rough 12/14/2021 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/20/2021 Approved OSVALDO PARAMO
Drywall Nailing 1/3/2022 Corrections Issued HAMIK HARTOUNIAN
Drywall Nailing 1/12/2022 Approved COREY HUPP
Final 2/28/2022 Corrections Issued HAMIK HARTOUNIAN
Green Building Final 2/28/2022 Corrections Issued HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 2/28/2022 Approved HAMIK HARTOUNIAN
Final 3/11/2022 Partial Inspection HAMIK HARTOUNIAN
Green Building Final 3/11/2022 Approved HAMIK HARTOUNIAN
Final 3/21/2022 OK to Issue CofO HAMIK HARTOUNIAN