1035 N LORD ST 90033

Certificate Information: 1035 N LORD ST 90033

Application / Permit
21016-10000-11382
Plan Check / Job No.
B21LA08386
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL KITCHEN AND DINING AREA PER ENGINEER DESIGN AND INSTALL NEW WINDOWS. "COMPLY WITH DEPARTMENT ORDER effective date 11/04/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 7/1/2021
Issuing Office
Current Status
Permit Finaled on 9/28/2021

Permit Application Status History

Submitted 5/3/2021 APPLICANT
Assigned to Plan Check Engineer 5/4/2021 GEORGE ALVAREZ
Corrections Issued 5/5/2021 GEORGE ALVAREZ
Applicant returned to address corrections 5/21/2021 LUKE GONZALES
Plan Check Approved 6/28/2021 GEORGE ALVAREZ
Issued 7/1/2021 APPLICANT
Building Plans Picked Up 7/2/2021 APPLICANT
Permit Finaled 9/27/2021 JEFFREY CORPUZ

Permit Application Clearance Information

Grading Pre-Inspection Cleared 6/11/2021 BRIAN MILLER

Contact Information

Contractor Carraher Norman Joseph Jr; Lic. No.: 813208-B 30175 ROYAL HUNT ST      MENIFEE, CA 92584
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

EDMUND LUM, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
LUCIANO GAUNA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
JAIME RIOS, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
ANDEY CHAPARRO, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
RYAN BARNES, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
PATRICK LIEBREGT, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GLEN RAND, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
SHAWN ESHBACH, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI
GABRIEL HERRERA, (213) 252-3962 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 7/7/2021 Partial Approval JEFFREY CORPUZ
ELECTRICAL-Rough 7/7/2021 Corrections Issued JEFFREY CORPUZ
Footing/Foundation/Slab 7/7/2021 Approved JEFFREY CORPUZ
Gas Test 7/7/2021 Approved JEFFREY CORPUZ
HVAC-Rough 7/7/2021 Corrections Issued JEFFREY CORPUZ
MERV13>=Rough 7/7/2021 Not Ready for Inspection JEFFREY CORPUZ
PLUMBING-Rough 7/7/2021 Corrections Issued JEFFREY CORPUZ
ELECTRICAL-Rough 7/14/2021 Approved JEFFREY CORPUZ
HVAC-Rough 7/14/2021 Approved JEFFREY CORPUZ
Interior/Exterior Lathing 7/14/2021 Approved JEFFREY CORPUZ
PLUMBING-Rough 7/14/2021 Approved JEFFREY CORPUZ
Insulation 7/22/2021 Approved JEFFREY CORPUZ
Drywall Nailing 7/26/2021 Approved JEFFREY CORPUZ
Interior/Exterior Lathing 7/26/2021 Approved JEFFREY CORPUZ
Gas Test 9/15/2021 Approved JEFFREY CORPUZ
PLUMBING-Final 9/15/2021 Not Ready for Inspection JEFFREY CORPUZ
BUILDING-Rough-Frame 9/27/2021 Approved JEFFREY CORPUZ
Final 9/27/2021 Permit Finaled JEFFREY CORPUZ
MERV13>=Final 9/27/2021 Approved JEFFREY CORPUZ
MERV13>=Rough 9/27/2021 Approved JEFFREY CORPUZ
SGSOV-Seismic Gas S/O Valve 9/27/2021 SGSOV Approved JEFFREY CORPUZ
Smoke Detectors 9/27/2021 Approved JEFFREY CORPUZ