838 1/2-840 W 66TH ST 90044

Certificate Information: 838 1/2-840 W 66TH ST 90044

Application / Permit
21016-10000-11179
Plan Check / Job No.
B21LA08251
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(2) Duplex
Work Description
CONVERT LAUNDRY ROOM TO ACCESSORY DWELLING UNIT PER CA GOVT CODE 65852.2(e)(1)(C)
Permit Issued
Issued on 9/6/2022
Issuing Office
Current Status
CofO Issued on 3/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/30/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 SERGIO GUTIERREZ
Corrections Issued 6/8/2021 SERGIO GUTIERREZ
Quality Review Completed 6/9/2021 FARUK SEZER
Green Plans Picked Up 2/7/2022 APPLICANT
Building Plans Picked Up 2/25/2022 APPLICANT
Applicant returned to address corrections 6/17/2022 SERGIO GUTIERREZ
Plan Check Approved 9/6/2022 SERGIO GUTIERREZ
Issued 9/6/2022 APPLICANT
CofO in Progress 1/27/2023 ALAN MORELOS
CofO Issued 3/13/2023 ERNESTO CORRAL
Permit Finaled 3/13/2023 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 8/2/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 8/2/2021 WALLIE JONG
Sewer availability Cleared 8/2/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/4/2021 WALLIE JONG
Green Code Cleared 2/3/2022 AARON COSTA
Tenant Habitability Plan Cleared 7/19/2022 MICHAEL SOTO
DAS Clearance Cleared 8/17/2022 SERGIO GUTIERREZ

Contact Information

Architect , ; Lic. No.: C36724       ,
Contractor Tennex Construction; Lic. No.: 1070554-B 1237 ARMACOST AVE #2      LOS ANGELES, CA 90025
Engineer Youm,, Moung Han; Lic. No.: C74086 309 S BERENDO ST APT 6      LOS ANGELES, CA 90020

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/9/2022 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 9/9/2022 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 9/20/2022 Partial Approval RUSSELL BONVOULOIR
Excavation/Setback/Form/Re-Bar 10/3/2022 Partial Approval RUSSELL BONVOULOIR
Footing/Foundation/Slab 10/3/2022 Partial Approval RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 11/28/2022 Partial Inspection RUSSELL BONVOULOIR
Green Building Rough 11/28/2022 Approved RUSSELL BONVOULOIR
Wood Frame 11/28/2022 Approved RUSSELL BONVOULOIR
Floor/Roof Diaphrgm/Shear Wall 12/2/2022 Approved RUSSELL BONVOULOIR
Drywall Nailing 12/5/2022 Approved ALAN MORELOS
Final 12/15/2022 Not Ready for Inspection ALAN MORELOS
Green Building Final 12/15/2022 Not Ready for Inspection ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 12/15/2022 SGSOV Not Ready ALAN MORELOS
Smoke Detectors 12/15/2022 Not Ready for Inspection ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 12/22/2022 SGSOV Not Ready ALAN MORELOS
Final 12/29/2022 Not Ready for Inspection DARRYL ARNOLD
Green Building Final 12/29/2022 Conditional Approval DARRYL ARNOLD
SGSOV-Seismic Gas S/O Valve 12/29/2022 SGSOV Not Ready DARRYL ARNOLD
Smoke Detectors 12/29/2022 Approved DARRYL ARNOLD
Final 1/10/2023 Corrections Issued ALAN MORELOS
Green Building Final 1/10/2023 Approved ALAN MORELOS
SGSOV-Seismic Gas S/O Valve 1/10/2023 SGSOV Approved ALAN MORELOS
Final 1/27/2023 OK to Issue CofO ALAN MORELOS