5511 E YORK BLVD 90042
Certificate Information: 5511 E YORK BLVD 90042
- Application / Permit
- 21016-10000-11144
- Plan Check / Job No.
- B21LA08220
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- CONVERT (E) MANUFACTURING BUILDING WITH ONE DWELLING UNIT INTO OFFICE BUILDING. INCLUDES ROOF FRAMING WORK.
- Permit Issued
- Issued on 11/2/2021
- Issuing Office
- Current Status
- CofO Issued on 12/30/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/5/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 5/6/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 8/27/2021 | SAMUEL GONZALEZ |
| Plan Check Approved | 10/20/2021 | RICARDO RAMIREZ |
| Issued | 11/2/2021 | APPLICANT |
| Building Plans Picked Up | 11/3/2021 | APPLICANT |
| CofO in Progress | 12/30/2022 | TED RIES |
| CofO Issued | 12/30/2022 | TED RIES |
| Permit Finaled | 12/30/2022 | TED RIES |
Permit Application Clearance Information
| "Q" conditions | Cleared | 6/15/2021 | MAXFIELD VERMY |
| Eng Process Fee Ord 176,300 | Cleared | 6/22/2021 | CELINA MORENO |
| Sewer availability | Cleared | 6/22/2021 | CELINA MORENO |
Contact Information
| Contractor | Advanced General Construction; Lic. No.: 951083-B | 6545 HAZELTINE AVE # 212 VAN NUYS, CA 91401 |
| Engineer | Shahbander,, Mohamad Nabil; Lic. No.: C61250 | 205 SAINT VINCENT IRVINE, CA 92618 |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 11/8/2021 | Approved | DANIEL COLLINS |
| Wood Frame | 11/22/2021 | Partial Approval | JONATHAN QUACH |
| Excavation/Setback/Form/Re-Bar | 12/3/2021 | Approved | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 12/3/2021 | Approved | BRUCE CAMPBELL |
| Excavation/Setback/Form/Re-Bar | 12/7/2021 | Not Ready for Inspection | MARK FERRARI |
| Footing/Foundation/Slab | 12/7/2021 | Not Ready for Inspection | MARK FERRARI |
| Insulation | 12/7/2021 | Not Ready for Inspection | MARK FERRARI |
| Insulation | 12/8/2021 | Not Ready for Inspection | MARK FERRARI |
| Deputy Wood Construction | 12/9/2021 | No Result Entered | RONALD PACHECO |
| Drywall Nailing | 12/10/2021 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 12/10/2021 | Corrections Issued | MARK FERRARI |
| Deputy Wood Construction | 12/13/2021 | Conditional Approval | RAFAEL ESPINOZA |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2021 | Approved | BRUCE CAMPBELL |
| Insulation | 12/15/2021 | Approved | MARK FERRARI |
| Interior/Exterior Lathing | 12/15/2021 | Approved | MARK FERRARI |
| Drywall Nailing | 12/16/2021 | Partial Approval | MARK FERRARI |
| Interior/Exterior Lathing | 12/16/2021 | Approved | MARK FERRARI |
| Drywall Nailing | 12/20/2021 | Approved | MARK FERRARI |
| Drywall Nailing | 12/21/2021 | Approved | MARK FERRARI |
| Pre-Inspection | 1/21/2022 | Conditional Approval | BRUCE CAMPBELL |
| Final | 5/24/2022 | Corrections Issued | MARK FERRARI |
| SGSOV-Seismic Gas S/O Valve | 5/24/2022 | SGSOV Not Ready | MARK FERRARI |
| Smoke Detectors | 5/24/2022 | Approved | MARK FERRARI |
| Wood Frame | 5/24/2022 | Approved | MARK FERRARI |
| Final | 10/20/2022 | Corrections Issued | RAFAEL ESPINOZA |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Approved | RAFAEL ESPINOZA |
| Final | 11/7/2022 | Conditional Approval | MARK FERRARI |
| Final | 12/22/2022 | Not Ready for Inspection | RAFAEL CORTES |
| Pre-Inspection | 12/27/2022 | Conditional Approval | RAFAEL CORTES |