7277 N VALJEAN AVE 91406
Certificate Information: 7277 N VALJEAN AVE 91406
- Application / Permit
- 21016-10000-11027
- Plan Check / Job No.
- B21LA08141
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (15) Telecommunication Transmitter - wireless
- Work Description
- T-MOBIBLE ROOFTOP SITE MODIFICATION. REMOVE/REPLACE (6) ANTENNAS WITH (9) NEW ANTENNAS. REMOVE/REPLACE (6) REMOTE RADIO UNITS WITH (9) NEW RRUS. REMOVE AND REPLACE (4) CABINETS WITH (2) NEW CABINETS. PER ZA-1996-0950-YV
- Permit Issued
- Issued on 3/18/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/7/2022
Permit Application Status History
| Submitted | 4/29/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/30/2021 | FERNANDO FLORES |
| Corrections Issued | 5/3/2021 | FERNANDO FLORES |
| Applicant returned to address corrections | 8/27/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 9/19/2021 | AUNG SOE |
| Plan Check Approved | 9/20/2021 | AUNG SOE |
| Issued | 3/18/2022 | APPLICANT |
| Building Plans Picked Up | 3/21/2022 | APPLICANT |
| Permit Finaled | 9/6/2022 | JEFFREY FULTON |
Permit Application Clearance Information
| "T" removal | Cleared | 8/4/2021 | CLAUDE GOODING |
| Miscellaneous | Cleared | 8/4/2021 | CLAUDE GOODING |
| ZA Case | Cleared | 8/4/2021 | CLAUDE GOODING |
| ZA Case | Cleared | 8/4/2021 | CLAUDE GOODING |
| ZA Case | Cleared | 8/4/2021 | CLAUDE GOODING |
| ZA Case | Cleared | 8/4/2021 | CLAUDE GOODING |
| ZA Case | Cleared | 8/4/2021 | CLAUDE GOODING |
| "Q" conditions | Cleared | 8/13/2021 | CLAUDE GOODING |
| City owned building/parcel | Cleared | 9/9/2021 | FERNANDO FLORES |
Contact Information
| Contractor | Telcom Engineering Group Llc; Lic. No.: 1075291-A | 473 US HWY 46 CLIFTON, NJ 07011 |
| Engineer | O'Sullivan,, Sean Michael; Lic. No.: C84392 | 25663 VIEW POINTE LAKE FOREST, CA 92630 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Final | 6/13/2022 | No Access for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 6/13/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 6/13/2022 | No Access for Inspection | JEFFREY FULTON |
| Final | 9/1/2022 | No Access for Inspection | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 9/1/2022 | SGSOV Not Ready | JEFFREY FULTON |
| Smoke Detectors | 9/1/2022 | No Access for Inspection | JEFFREY FULTON |
| Final | 9/6/2022 | Permit Finaled | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 9/6/2022 | SGSOV Approved | JEFFREY FULTON |
| Smoke Detectors | 9/6/2022 | Approved | JEFFREY FULTON |