438-438 1/2 S SERRANO AVE 90020

Certificate Information: 438-438 1/2 S SERRANO AVE 90020

Application / Permit
21016-10000-10990
Plan Check / Job No.
B21LA08105
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ePlan CONVERT A PORTION OF (E) SFD (346 SF) INTO A JUNIOR ADU PER STATE LAW GCS 65852.2(e)(1)(A). SCOPE WILL ALSO INCLUDE A REMODEL TO (E) SFD.
Permit Issued
Issued on 1/30/2023
Issuing Office
Current Status
CofO Issued on 8/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 6/3/2021 MICHAEL LOPEZ
Corrections Issued 6/11/2021 MICHAEL LOPEZ
Quality Review Completed 6/17/2021 HERNAN ARREOLA
Applicant returned to address corrections 8/7/2021 MICHAEL LOPEZ
Applicant returned to address corrections 1/5/2022 MICHAEL LOPEZ
Applicant returned to address corrections 1/26/2022 MICHAEL LOPEZ
Applicant returned to address corrections 3/10/2022 MICHAEL LOPEZ
Plan Check Approved 5/11/2022 MICHAEL LOPEZ
Issued 1/30/2023 APPLICANT
CofO in Progress 7/10/2023 JEFFREY MEAD
Permit Finaled 8/9/2023 DEROLD HAUFF
CofO Issued 8/9/2023 DEROLD HAUFF
Permit Finaled 8/9/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/29/2021 THOMAS LANG
City Hist. Cultural Monument Cleared 7/1/2021 LAMBERT GIESSINGER
Historic monument Cleared 7/1/2021 LAMBERT GIESSINGER
Eng Process Fee Ord 176,300 Cleared 7/27/2021 THOMAS LANG
Sewer availability Cleared 7/27/2021 THOMAS LANG

Contact Information

Contractor Owner-Builder       ,
Engineer Mina,, Joseph; Lic. No.: C53465 7247 DARNOCH WY      WEST HILLS, CA 91307

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

ELECTRICAL-Rough 4/7/2023 Approved JEFFREY MEAD
HVAC-Rough 4/7/2023 Partial Approval JEFFREY MEAD
PLUMBING-Rough 4/7/2023 Not Ready for Inspection JEFFREY MEAD
BUILDING-Rough-Frame 4/10/2023 Corrections Issued JEFFREY MEAD
BUILDING-Rough-Frame 4/18/2023 Partial Approval JEFFREY MEAD
Drywall Nailing 4/27/2023 Partial Approval ALIZAH MAYAGOITIA
HVAC-Rough 4/27/2023 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 4/27/2023 Approved ALIZAH MAYAGOITIA
HVAC-Rough 4/28/2023 Approved LILIANA PORTILLO
Insulation 4/28/2023 Approved LILIANA PORTILLO
Drywall Nailing 5/2/2023 Approved RICHARD DOCKUS
ELECTRICAL-Final 7/3/2023 Corrections Issued JEFFREY MEAD
HVAC-Final 7/3/2023 Corrections Issued JEFFREY MEAD
PLUMBING-Final 7/3/2023 Approved JEFFREY MEAD
BUILDING-Rough-Frame 7/7/2023 Approved JEFFREY MEAD
ELECTRICAL-Final 7/7/2023 Approved JEFFREY MEAD
Final 7/7/2023 OK to Issue CofO JEFFREY MEAD
HVAC-Final 7/7/2023 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 7/7/2023 SGSOV Approved JEFFREY MEAD
Smoke Detectors 7/7/2023 Approved JEFFREY MEAD