11605 W REGENT ST 90066

Certificate Information: 11605 W REGENT ST 90066

Application / Permit
21016-10000-10988
Plan Check / Job No.
B21LA08104
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan Convert existing detached garage into an accessory dwelling unit per GCS 65852.2(E)(1)(A) COMPLY WITH DEPARTMENT ORDER effective date 03/08/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 9/7/2021
Issuing Office
Current Status
CofO Issued on 6/30/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/29/2021 APPLICANT
Assigned to Plan Check Engineer 4/30/2021 MONICA RAMIREZ
Corrections Issued 4/30/2021 MONICA RAMIREZ
Applicant returned to address corrections 8/26/2021 MONICA RAMIREZ
Plan Check Approved 8/31/2021 MONICA RAMIREZ
Issued 9/7/2021 APPLICANT
CofO in Progress 6/21/2022 RYAN BARNES
Permit Finaled 6/30/2022 BRUCE TODD
CofO Issued 6/30/2022 BRUCE TODD
Permit Finaled 6/30/2022 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 6/8/2021 SAUL GARCIA
Sewer availability Cleared 6/8/2021 SAUL GARCIA
Eng Process Fee Ord 176,300 Cleared 6/9/2021 SAUL GARCIA
Construction within easement Cleared 6/26/2021 RIDWAN HARDY
Specific Plan Cleared 7/14/2021 PEDRO AYALA
Construction near power lines Cleared 8/16/2021 WALTER RAMIREZ

Contact Information

Contractor Owner-Builder       ,
Engineer Wu,, Harold Ping-Hung; Lic. No.: C35693 1168 SAN GABRIEL BLVD NO N      ROSEMEAD, CA 91770

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/24/2021 Approved MARIAN PODPORA
Sewer 9/24/2021 Not Ready for Inspection MARIAN PODPORA
Sewer 9/28/2021 Approved RYAN BARNES
Excavation/Setback/Form/Re-Bar 9/30/2021 Approved RYAN BARNES
BUILDING-Rough-Frame 10/14/2021 Partial Approval RYAN BARNES
Interior/Exterior Lathing 10/18/2021 Corrections Issued RYAN BARNES
Interior/Exterior Lathing 10/19/2021 Approved RYAN BARNES
Underground Mechanical 10/19/2021 Approved RYAN BARNES
ELECTRICAL-Rough 10/27/2021 Corrections Issued RYAN BARNES
HVAC-Rough 10/27/2021 Corrections Issued RYAN BARNES
PLUMBING-Rough 10/27/2021 Corrections Issued RYAN BARNES
ELECTRICAL-Rough 10/28/2021 Approved RYAN BARNES
HVAC-Rough 10/28/2021 Approved RYAN BARNES
PLUMBING-Rough 10/28/2021 Approved RYAN BARNES
Insulation 11/1/2021 Approved RYAN BARNES
Drywall Nailing 11/4/2021 Approved RYAN BARNES
Floor/Roof Diaphrgm/Shear Wall 11/9/2021 Approved RYAN BARNES
Interior/Exterior Lathing 11/15/2021 Approved RYAN BARNES
BUILDING-Rough-Frame 2/28/2022 Approved RYAN BARNES
Final 2/28/2022 Conditional Approval RYAN BARNES
SGSOV-Seismic Gas S/O Valve 2/28/2022 SGSOV Approved RYAN BARNES
Smoke Detectors 2/28/2022 Approved RYAN BARNES