2204 N EASTERN AVE 90032
Certificate Information: 2204 N EASTERN AVE 90032
- Application / Permit
- 21016-10000-10859
- Plan Check / Job No.
- B21LA08034
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE TO ADU PER GCS 65862.2(e)(1)(A)
- Permit Issued
- Issued on 11/5/2021
- Issuing Office
- Current Status
- CofO Issued on 6/18/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | LUKE GONZALES |
| Corrections Issued | 4/29/2021 | LUKE GONZALES |
| Applicant returned to address corrections | 9/5/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 10/13/2021 | RAMA DABADGE |
| Plan Check Approved | 10/14/2021 | RAMA DABADGE |
| Issued | 11/5/2021 | APPLICANT |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| CofO in Progress | 6/13/2022 | AMY COLIN |
| Permit Finaled | 6/18/2022 | DEROLD HAUFF |
| CofO Issued | 6/18/2022 | DEROLD HAUFF |
| Permit Finaled | 6/18/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 5/12/2021 | THOMAS LANG |
| Sewer availability | Cleared | 5/12/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2021 | THOMAS LANG |
| "D" conditions | Cleared | 6/14/2021 | JOE LUCKEY |
| "Q" conditions | Cleared | 6/14/2021 | JOE LUCKEY |
| Construction near power lines | Cleared | 7/19/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Edward Guojun; Lic. No.: C56706 | 1107 FAIR OAKS AVE 118 SOUTH PASADENA, CA 91030 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 2/15/2022 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 2/15/2022 | Corrections Issued | COREY HUPP |
| PLUMBING-Rough | 2/15/2022 | Corrections Issued | COREY HUPP |
| Footing/Foundation/Slab | 2/22/2022 | Approved | COREY HUPP |
| ELECTRICAL-Rough | 3/7/2022 | Approved | COREY HUPP |
| Gas Test | 3/7/2022 | Approved | COREY HUPP |
| HVAC-Rough | 3/15/2022 | Approved | AMY COLIN |
| BUILDING-Rough-Frame | 3/16/2022 | Approved | AMY COLIN |
| Green Building Rough | 3/16/2022 | Approved | AMY COLIN |
| PLUMBING-Rough | 3/16/2022 | Approved | AMY COLIN |
| Shower Pan | 3/16/2022 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 3/17/2022 | Approved | AMY COLIN |
| Insulation | 3/22/2022 | Approved | ALIZAH MAYAGOITIA |
| Drywall Nailing | 3/31/2022 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 3/31/2022 | Approved | AMY COLIN |
| Service/Power Release | 3/31/2022 | Not Ready for Inspection | AMY COLIN |
| Final | 5/2/2022 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 5/2/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 5/2/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Smoke Detectors | 5/2/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| ELECTRICAL-Final | 5/16/2022 | Corrections Issued | AMY COLIN |
| Final | 5/16/2022 | Partial Inspection | AMY COLIN |
| Gas Test | 5/16/2022 | Corrections Issued | AMY COLIN |
| Green Building Final | 5/16/2022 | Approved | AMY COLIN |
| HVAC-Final | 5/16/2022 | Approved | AMY COLIN |
| PLUMBING-Final | 5/16/2022 | Approved | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 5/16/2022 | SGSOV Approved | AMY COLIN |
| Smoke Detectors | 5/16/2022 | Approved | AMY COLIN |
| ELECTRICAL-Final | 5/24/2022 | Corrections Issued | RUBEN SALAS |
| Final | 6/1/2022 | Partial Inspection | AMY COLIN |
| Final | 6/13/2022 | OK to Issue CofO | AMY COLIN |