1735-1737 S WARNALL AVE 90024

Certificate Information: 1735-1737 S WARNALL AVE 90024

Application / Permit
21016-10000-10681
Plan Check / Job No.
B21LA07884
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SFD ADDITION AND ADU (480 SF) ADDITION TO EXISTING SFD WITH GARAGE PER 12.22 A33 C & E
Permit Issued
Issued on 12/13/2021
Issuing Office
Current Status
CofO Issued on 3/17/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 STARR CHEN
Corrections Issued 6/2/2021 STARR CHEN
Quality Review Completed 6/7/2021 ALLEN MANALANSAN
Building Plans Picked Up 6/9/2021 APPLICANT
Applicant returned to address corrections 6/25/2021 STARR CHEN
Applicant returned to address corrections 8/27/2021 STARR CHEN
Applicant returned to address corrections 9/8/2021 STARR CHEN
Plan Check Approved 11/18/2021 STARR CHEN
Issued 12/13/2021 APPLICANT
CofO in Progress 3/14/2025 DANIEL VERA
CofO Issued 3/17/2025 RICHARD STEINBACH
Permit Finaled 3/17/2025 RICHARD STEINBACH

Permit Application Clearance Information

Address approval Cleared 8/3/2021 WALLIE JONG
Roof/Waste drainage to street Cleared 8/3/2021 WALLIE JONG
Eng Process Fee Ord 176,300 Cleared 8/5/2021 WALLIE JONG
Sewer availability Cleared 8/5/2021 WALLIE JONG
Grading Pre-Inspection Cleared 8/11/2021 PATRICK MISCHLICH
Specific Plan Cleared 8/12/2021 KEVIN ARUCAN
Miscellaneous Cleared 9/8/2021 STARR CHEN
GPI Written Notices Cleared 11/18/2021 STARR CHEN

Contact Information

Architect , ; Lic. No.: C39293 134 S GLASSELL   STE E    ORANGE, CA 92866
Contractor Doug'S Remodeling; Lic. No.: 989936-B 9936 SEPULVEDA BLVD #1      MISSION HILLS, CA 91345
Engineer Daoud,, Richard Antoine; Lic. No.: S6585 714 W OLYMPIC BLVD STE 617      LOS ANGELES, CA 90015

Inspector Information

DAVID SCANTLIN, (310) 914-3863 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 1/21/2022 Conditional Approval BRENDAN LOONEY
Pre-Inspection 1/21/2022 Approved BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 2/17/2022 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 2/17/2022 Not Ready for Inspection BRENDAN LOONEY
METHANE-Barrier 2/17/2022 Approved BRENDAN LOONEY
METHANE-Subgrade 2/17/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 2/17/2022 Corrections Issued BRENDAN LOONEY
Sewer 2/17/2022 Not Ready for Inspection BRENDAN LOONEY
Excavation/Setback/Form/Re-Bar 2/28/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 2/28/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 2/28/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Excavation/Setback/Form/Re-Bar 3/3/2022 Corrections Issued BRENDAN LOONEY
Footing/Foundation/Slab 3/3/2022 Corrections Issued BRENDAN LOONEY
PLUMBING-Rough 3/3/2022 Not Ready for Inspection BRENDAN LOONEY
Footing/Foundation/Slab 3/8/2022 Approved BRENDAN LOONEY
PLUMBING-Rough 3/8/2022 Partial Approval BRENDAN LOONEY
BUILDING-Rough-Frame 9/6/2022 Corrections Issued STEPHANIE SWANSON
Deputy Wood Construction 12/8/2022 Conditional Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 12/9/2022 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 12/9/2022 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 12/9/2022 Corrections Issued STEPHANIE SWANSON
METHANE-Rough 12/9/2022 Approved STEPHANIE SWANSON
PLUMBING-Rough 12/9/2022 Corrections Issued STEPHANIE SWANSON
Special/Order Compliance 2/7/2023 Partial Inspection MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 2/8/2023 Partial Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 3/17/2023 Approved MICHAEL PELHAM
Special/Order Compliance 4/24/2023 Corrections Issued MICHAEL PELHAM
Special/Order Compliance 4/24/2023 Partial Inspection STEPHANIE SWANSON
Special/Order Compliance 6/20/2023 Partial Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 7/13/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 7/13/2023 Corrections Issued STEPHANIE SWANSON
HVAC-Rough 7/13/2023 Approved STEPHANIE SWANSON
PLUMBING-Rough 7/13/2023 Corrections Issued STEPHANIE SWANSON
Shower Pan 7/13/2023 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Rough 8/1/2023 Partial Approval STEPHANIE SWANSON
HVAC-Rough 8/1/2023 Approved STEPHANIE SWANSON
Insulation 8/1/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 8/1/2023 Conditional Approval STEPHANIE SWANSON
PLUMBING-Rough 8/1/2023 Not Ready for Inspection STEPHANIE SWANSON
Shower Pan 8/1/2023 Not Ready for Inspection STEPHANIE SWANSON
BUILDING-Rough-Frame 8/16/2023 Approved STEPHANIE SWANSON
Final 8/16/2023 Corrections Issued STEPHANIE SWANSON
Green Building Rough 8/16/2023 Approved STEPHANIE SWANSON
Interior/Exterior Lathing 8/16/2023 Approved STEPHANIE SWANSON
PLUMBING-Rough 8/16/2023 Approved STEPHANIE SWANSON
Shower Pan 8/16/2023 Approved STEPHANIE SWANSON
Drywall Nailing 8/31/2023 Corrections Issued STEPHANIE SWANSON
Interior/Exterior Lathing 8/31/2023 Approved STEPHANIE SWANSON
Special/Order Compliance 9/11/2023 Partial Inspection MICHAEL PELHAM
Special/Order Compliance 4/3/2024 Not Ready for Inspection MICHAEL PELHAM
Special/Order Compliance 7/24/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 8/28/2024 Corrections Issued STEPHANIE SWANSON
Final 8/28/2024 Not Ready for Inspection STEPHANIE SWANSON
Green Building Final 8/28/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 8/28/2024 Not Ready for Inspection STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 8/28/2024 SGSOV Not Ready STEPHANIE SWANSON
Service/Power Release 8/28/2024 Not Ready for Inspection STEPHANIE SWANSON
Smoke Detectors 8/28/2024 Corrections Issued STEPHANIE SWANSON
ELECTRICAL-Final 9/3/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 9/6/2024 Approved STEPHANIE SWANSON
PLUMBING-Final 9/6/2024 Corrections Issued STEPHANIE SWANSON
Service/Power Release 9/6/2024 Approved STEPHANIE SWANSON
Smoke Detectors 9/6/2024 Approved STEPHANIE SWANSON
Service/Power Release 9/20/2024 Approved STEPHANIE SWANSON
Final 1/10/2025 Corrections Issued STEPHANIE SWANSON
HVAC-Final 1/10/2025 Approved STEPHANIE SWANSON
PLUMBING-Final 1/10/2025 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 1/10/2025 SGSOV Not Ready STEPHANIE SWANSON
Final 2/20/2025 Corrections Issued STEPHANIE SWANSON
SGSOV-Seismic Gas S/O Valve 2/20/2025 SGSOV Approved STEPHANIE SWANSON
Final 3/12/2025 Not Ready for Inspection DANIEL VERA
Final 3/13/2025 OK to Issue CofO DANIEL VERA
PLUMBING-Final 3/13/2025 Approved DANIEL VERA