920 S ABBOT KINNEY BLVD 90291

Certificate Information: 920 S ABBOT KINNEY BLVD 90291

Application / Permit
21016-10000-10627
Plan Check / Job No.
B21LA07814
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(15) Telecommunication Transmitter - wireless
Work Description
MODIFICATION ON A CELL TOWER THAT CONSISTS OF UPGRADING TWO PANEL ANTENNAS, UPGRADING THREE REMOTE RADIO UNITS, UPGRADING HYBRID CABLES ***"COMPLY WITH DEPARTMENT ORDER effective date 03/04/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE".
Permit Issued
Issued on 2/3/2022
Issuing Office
Current Status
Permit Finaled on 2/21/2025

Permit Application Status History

Submitted 4/27/2021 APPLICANT
Assigned to Plan Check Engineer 4/28/2021 RICARDO RAMIREZ
Corrections Issued 4/28/2021 RICARDO RAMIREZ
Applicant returned to address corrections 8/9/2021 RACHEL BEYENE
Plan Check Approved 1/13/2022 CHRISTOPHER KOMANCHECK
Issued 2/3/2022 APPLICANT
Building Plans Picked Up 2/11/2022 APPLICANT
Permit Finaled 2/21/2025 FARHAD DADBIN

Permit Application Clearance Information

Miscellaneous Cleared 7/21/2021 CLAUDE GOODING
Miscellaneous Cleared 7/21/2021 CLAUDE GOODING
Miscellaneous Cleared 7/21/2021 CLAUDE GOODING
Miscellaneous Cleared 7/21/2021 CLAUDE GOODING
Miscellaneous Cleared 7/21/2021 CLAUDE GOODING
Plan Approval Cleared 7/21/2021 CLAUDE GOODING
ZA Case Cleared 7/21/2021 CLAUDE GOODING
ZA Case Cleared 7/21/2021 CLAUDE GOODING
Coastal Zone Cleared 7/23/2021 BINDU KANNAN
Miscellaneous Cleared 7/23/2021 BINDU KANNAN
Specific Plan Cleared 7/23/2021 BINDU KANNAN
ZI Cleared 7/23/2021 BINDU KANNAN
Tenant Habitability Plan Cleared 7/26/2021 ISMAEL HERNANDEZ

Contact Information

Contractor Sitesol; Lic. No.: 948463-B PO BOX 91747      LONG BEACH, CA 90809
Engineer Holmes,, Wells Lind; Lic. No.: S6203 2379 W. 275 N.      LEHI, UT 84043

Inspector Information

FARHAD DADBIN, (310) 914-3922 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Not Ready FARHAD DADBIN
Smoke Detectors 6/26/2023 Not Ready for Inspection FARHAD DADBIN
Special/Order Compliance 12/1/2023 Partial Inspection FARHAD DADBIN
Final 12/19/2024 Not Ready for Inspection FARHAD DADBIN
SGSOV-Seismic Gas S/O Valve 12/19/2024 SGSOV No Gas FARHAD DADBIN
Smoke Detectors 12/19/2024 Not Ready for Inspection FARHAD DADBIN
Final 2/21/2025 Permit Finaled FARHAD DADBIN
Smoke Detectors 2/21/2025 Approved FARHAD DADBIN