2200 S 6TH AVE 90018
Certificate Information: 2200 S 6TH AVE 90018
- Application / Permit
- 21016-10000-10574
- Plan Check / Job No.
- B21LA07749
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: Soft-Story seismic retrofit per LABC Chapter 93: INSTALL NEW (2) SPECIAL STEEL CANTILEVER COLUMNS & (1) ORDINARY MOMENT FRAME.
- Permit Issued
- Issued on 8/18/2021
- Issuing Office
- Current Status
- CofC Issued on 11/9/2022
Permit Application Status History
| Submitted | 4/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/20/2021 | HANS SANTIAGO |
| Corrections Issued | 5/24/2021 | HANS SANTIAGO |
| Quality Review Completed | 5/26/2021 | SAI KHUM |
| Applicant returned to address corrections | 6/15/2021 | HANS SANTIAGO |
| Plan Check Approved | 7/19/2021 | ANDREW SANTIAGO |
| Issued | 8/18/2021 | APPLICANT |
| OK for CofC | 11/2/2021 | DARRYL ARNOLD |
| CofC Issued | 11/9/2022 | ERNESTO CORRAL |
Permit Application Clearance Information
| Community Plan Implem. Overlay | Cleared | 7/14/2021 | KYLE WINSTON |
| Tenant Habitability Plan | Cleared | 7/29/2021 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Titan Contracting Services Inc; Lic. No.: 976552-B | 13434 RAYMER STREET NORTH HOLLYWOOD, CA 91605 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 743 S SIERRA VISTA AVE C ALHAMBRA, CA 91801 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/2/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Pre-Inspection | 9/9/2021 | Corrections Issued | DARRYL ARNOLD |
| Deputy Steel/Welding | 9/27/2021 | Conditional Approval | BRUCE CAMPBELL |
| Footing/Foundation/Slab | 10/1/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/1/2021 | Corrections Issued | DARRYL ARNOLD |
| Structural Steel Frame | 10/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/15/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/18/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 11/2/2021 | OK for CofC | DARRYL ARNOLD |
| METHANE-Final | 11/2/2021 | Approved | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 11/2/2021 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 11/2/2021 | Approved | DARRYL ARNOLD |