3266-3268 N DREW ST 90065
Certificate Information: 3266-3268 N DREW ST 90065
- Application / Permit
- 21016-10000-10569
- Plan Check / Job No.
- B21LA07731
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- CONVERSION OF (E) BEDROOM WITHIN (E) UNIT INTO AN ACCESSORY DWELLING UNIT (288 SF) PER LAMC 12.22 A.33(c) AND (e).
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/10/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 5/10/2021 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 7/29/2021 | RICARDO RAMIREZ |
| Issued | 8/13/2021 | APPLICANT |
| Building Plans Picked Up | 8/16/2021 | APPLICANT |
| CofO in Progress | 8/28/2023 | RAFAEL CORTES |
| CofO Issued | 9/5/2023 | TED RIES |
| Permit Finaled | 9/5/2023 | TED RIES |
Permit Application Clearance Information
| Sewer availability | Cleared | 6/24/2021 | RENZ SORIANO |
| Address approval | Cleared | 6/25/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 6/25/2021 | RENZ SORIANO |
| Supp. Use District POD/CDO/TDO | Cleared | 7/1/2021 | ADRINEH MELKONIAN |
| Tenant Habitability Plan | Cleared | 7/6/2021 | PHILLIP MUNGUIA |
| ZA Case | Cleared | 7/6/2021 | MAXFIELD VERMY |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SEAN POMISH, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAFAEL CORTES, (213) 202-2643 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 3/10/2022 | Corrections Issued | MARK FERRARI |
| Wood Frame | 4/26/2022 | Not Ready for Inspection | MARK FERRARI |
| Wood Frame | 11/4/2022 | Approved | MARK FERRARI |
| Drywall Nailing | 11/21/2022 | Approved | MARK FERRARI |
| Final | 4/27/2023 | Not Ready for Inspection | RAFAEL CORTES |
| SGSOV-Seismic Gas S/O Valve | 4/27/2023 | SGSOV Not Ready | RAFAEL CORTES |
| Smoke Detectors | 4/27/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 6/21/2023 | Not Ready for Inspection | JEROME BLACKWOOD |
| SGSOV-Seismic Gas S/O Valve | 6/21/2023 | SGSOV Approved | JEROME BLACKWOOD |
| Smoke Detectors | 6/21/2023 | Approved | JEROME BLACKWOOD |
| Final | 8/9/2023 | Not Ready for Inspection | RAFAEL CORTES |
| Final | 8/25/2023 | OK to Issue CofO | RAFAEL CORTES |