2312 W 48TH ST 90043
Certificate Information: 2312 W 48TH ST 90043
- Application / Permit
- 21016-10000-10516
- Plan Check / Job No.
- B21LA07660
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- Commercial
- Primary Use
- (16) Retail
- Work Description
- Scope of work to include: (1) Addition to (E) Retail building for storage, cashier's area, restroom, and utility room.No Change in Use or Occupancy.
- Permit Issued
- Issued on 2/21/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 10/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 6/3/2021 | ZAW HAN |
| Disabled Access Plans Picked Up | 6/7/2021 | APPLICANT |
| Corrections Issued | 6/8/2021 | ZAW HAN |
| Quality Review Completed | 6/15/2021 | WING SUEN |
| Building Plans Picked Up | 6/21/2021 | APPLICANT |
| Applicant returned to address corrections | 9/27/2021 | ZAW HAN |
| Applicant returned to address corrections | 11/22/2021 | ZAW HAN |
| Applicant returned to address corrections | 1/7/2022 | ZAW HAN |
| Applicant returned to address corrections | 3/8/2022 | ZAW HAN |
| Applicant returned to address corrections | 10/26/2022 | ZAW HAN |
| Applicant returned to address corrections | 12/13/2022 | ZAW HAN |
| Applicant returned to address corrections | 12/14/2022 | ZAW HAN |
| Applicant returned to address corrections | 12/21/2022 | ZAW HAN |
| Applicant returned to address corrections | 12/27/2022 | ZAW HAN |
| Applicant returned to address corrections | 2/9/2023 | ZAW HAN |
| Plan Check Approved | 2/16/2023 | ZAW HAN |
| Issued | 2/21/2023 | APPLICANT |
| Permit Closed-Status Void | 8/25/2025 | ERNESTO CORRAL |
| Re-Activate Permit | 10/7/2025 | ERNESTO CORRAL |
| CofO in Progress | 10/10/2025 | ERNESTO CORRAL |
| Permit Finaled | 10/10/2025 | ERNESTO CORRAL |
| CofO Issued | 10/10/2025 | ERNESTO CORRAL |
| Permit Finaled | 10/10/2025 | ERNESTO CORRAL |
Permit Application Clearance Information
| Sewer availability | Cleared | 4/21/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 4/25/2022 | JEANIE LAM |
| Highway dedication | Cleared | 5/23/2022 | JEANIE LAM |
| Food Service Establishment | Cleared | 5/25/2022 | PAWAN VERMA |
| Community Plan Implem. Overlay | Cleared | 9/27/2022 | KYLE WINSTON |
| ZI | Cleared | 9/27/2022 | KYLE WINSTON |
| DAS Clearance | Cleared | 10/31/2022 | ZAW HAN |
| Green Code | Cleared | 12/14/2022 | ZAW HAN |
| Food establishment approval | Cleared | 12/16/2022 | LACDHS APPROVED |
| Roof/Waste drainage to street | Cleared | 12/16/2022 | JEANIE LAM |
| ZA Case | Cleared | 12/20/2022 | ANACANY HURTADO |
Contact Information
| Architect | Kim,, Hoejun; Lic. No.: C37047 | 288 S. 2ND AVENUE, #B ARCADIA, CA 91006 |
| Contractor | Entheos Design Group Inc; Lic. No.: 940871-B | 5295 CAMERON DR #501 BUENA PARK, CA 90621 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 7/12/2023 | No Result Entered | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 7/24/2023 | Not Ready for Inspection | ALAN MORELOS |
| Deputy Drilled-In Anchors | 8/1/2023 | No Result Entered | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 8/4/2023 | Conditional Approval | MARTIN TAVITIAN |
| Pre-Inspection | 8/4/2023 | Conditional Approval | MARTIN TAVITIAN |
| Excavation/Setback/Form/Re-Bar | 8/7/2023 | Approved | MARTIN TAVITIAN |
| Green Building Rough | 9/14/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 9/14/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Green Building Rough | 9/26/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Wood Frame | 9/26/2023 | Not Ready for Inspection | MARTIN TAVITIAN |
| Interior/Exterior Lathing | 10/27/2023 | Approved | MARTIN TAVITIAN |
| Special/Order Compliance | 10/27/2023 | Approved | MARTIN TAVITIAN |
| Drywall Nailing | 12/29/2023 | Approved | MARTIN TAVITIAN |
| Green Building Rough | 12/29/2023 | Approved | MARTIN TAVITIAN |
| Final | 7/1/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Footing/Foundation/Slab | 7/1/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Green Building Final | 7/1/2024 | Conditional Approval | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 7/1/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 7/1/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 7/1/2024 | Conditional Approval | DARRYL ARNOLD |
| Final | 8/20/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Footing/Foundation/Slab | 8/20/2024 | Approved | ALFREDO LOPEZ |
| Green Building Final | 8/20/2024 | Approved | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 8/20/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 8/20/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Wood Frame | 8/20/2024 | Not Ready for Inspection | ALFREDO LOPEZ |
| Final | 8/23/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 8/23/2024 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 8/23/2024 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 8/23/2024 | Not Ready for Inspection | DARRYL ARNOLD |
| Final | 9/12/2024 | Partial Inspection | ALFREDO LOPEZ |
| SGSOV-Seismic Gas S/O Valve | 9/12/2024 | SGSOV Not Ready | ALFREDO LOPEZ |
| Smoke Detectors | 9/12/2024 | Approved | ALFREDO LOPEZ |
| Wood Frame | 9/12/2024 | Approved | ALFREDO LOPEZ |
| Final | 10/10/2025 | OK to Issue CofO | ERNESTO CORRAL |
| SGSOV-Seismic Gas S/O Valve | 10/10/2025 | SGSOV Approved | ERNESTO CORRAL |