105 E ROSE AVE 90291
Certificate Information: 105 E ROSE AVE 90291
- Application / Permit
- 21016-10000-10464
- Plan Check / Job No.
- B21LA07612
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- REMODEL TO (E) DUPLEX. NEW DECK AND STAIRS AT REAR.
- Permit Issued
- Issued on 8/13/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/19/2022
Permit Application Status History
| Submitted | 4/26/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | KEVIN MORALES |
| Corrections Issued | 6/2/2021 | KEVIN MORALES |
| Quality Review Completed | 6/7/2021 | EUGENE BARBEAU |
| Plan Check Approved | 8/13/2021 | KEVIN MORALES |
| Issued | 8/13/2021 | APPLICANT |
| Building Plans Picked Up | 8/17/2021 | APPLICANT |
| Permit Finaled | 12/6/2022 | EVAN COOPER |
| CofO in Progress | 12/7/2022 | EVAN COOPER |
| CofO in Progress | 12/19/2022 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 7/21/2021 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 7/21/2021 | HISASHI KOBAYAKAWA |
| Specific Plan | Cleared | 7/23/2021 | BINDU KANNAN |
| Coastal Zone | Cleared | 8/11/2021 | KENTON TRINH |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Acciani,, Mark; Lic. No.: C83929 | PO BOX 1390 RUNNING SPRINGS, CA 92382 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 9/24/2021 | Approved | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/17/2021 | Partial Approval | DAVID FEILER |
| ELECTRICAL-Rough | 12/17/2021 | Partial Approval | DAVID FEILER |
| METHANE-Rough | 12/17/2021 | Approved | DAVID FEILER |
| PLUMBING-Rough | 12/17/2021 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 1/21/2022 | Partial Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 1/21/2022 | Approved | DAVID FEILER |
| HVAC-Rough | 1/21/2022 | Approved | DAVID FEILER |
| Shower Pan | 1/21/2022 | Approved | DAVID FEILER |
| Drywall Nailing | 1/28/2022 | Approved | DAVID FEILER |
| Interior/Exterior Lathing | 3/11/2022 | Approved | DAVID FEILER |
| Wood Frame | 4/28/2022 | Approved | DAVID FEILER |
| BUILDING-Rough-Frame | 11/8/2022 | Approved | ANDREW NAVE |
| ELECTRICAL-Final | 11/8/2022 | Corrections Issued | ANDREW NAVE |
| Final | 11/8/2022 | Corrections Issued | ANDREW NAVE |
| HVAC-Final | 11/8/2022 | Approved | ANDREW NAVE |
| PLUMBING-Final | 11/8/2022 | Corrections Issued | ANDREW NAVE |
| SGSOV-Seismic Gas S/O Valve | 11/8/2022 | SGSOV Not Ready | ANDREW NAVE |
| Smoke Detectors | 11/8/2022 | Corrections Issued | ANDREW NAVE |
| ELECTRICAL-Final | 11/29/2022 | Approved | DAVID FEILER |
| Final | 11/29/2022 | Partial Inspection | DAVID FEILER |
| PLUMBING-Final | 11/29/2022 | Partial Inspection | DAVID FEILER |
| SGSOV-Seismic Gas S/O Valve | 11/29/2022 | SGSOV Approved | DAVID FEILER |
| Smoke Detectors | 11/29/2022 | Approved | DAVID FEILER |
| Final | 12/6/2022 | Permit Finaled | EVAN COOPER |
| PLUMBING-Final | 12/6/2022 | Approved | EVAN COOPER |
| Special/Order Compliance | 12/6/2022 | Partial Inspection | JEREMY TODD |