22722 W NAPA ST 91304
Certificate Information: 22722 W NAPA ST 91304
- Application / Permit
- 21016-10000-10410
- Plan Check / Job No.
- B21LA07578
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT EXISTING GARAGE TO ADU 441 SQ FT PER GCS 65852.2(e)(1)(a). All work per WOOD FRAME PRESCRIPTIVE DESIGN.
- Permit Issued
- Issued on 10/22/2021
- Issuing Office
- Current Status
- CofO Issued on 6/1/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/27/2021 | ZAW HAN |
| Corrections Issued | 4/29/2021 | ZAW HAN |
| Applicant returned to address corrections | 6/2/2021 | RICARDO RAMIREZ |
| Applicant returned to address corrections | 7/22/2021 | ZAW HAN |
| Plan Check Approved | 7/26/2021 | ZAW HAN |
| Building Plans Picked Up | 10/13/2021 | APPLICANT |
| Issued | 10/22/2021 | APPLICANT |
| CofO in Progress | 5/18/2022 | CHRIS CHRISTENSEN |
| CofO Issued | 6/1/2022 | MICHAEL SMITH |
| Permit Finaled | 6/1/2022 | MICHAEL SMITH |
Permit Application Clearance Information
| Address approval | Cleared | 5/26/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/26/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/26/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/26/2021 | GABRIEL ROBLES |
| Construction near power lines | Cleared | 7/9/2021 | OSCAR CASTRO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JEFFREY HARTLINE, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
| CHRIS CHRISTENSEN, (818) 774-4320 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/28/2021 | Conditional Approval | DAVID STEPANYAN |
| Footing/Foundation/Slab | 11/1/2021 | Corrections Issued | DAVID STEPANYAN |
| Footing/Foundation/Slab | 11/4/2021 | Approved | DAVID STEPANYAN |
| PLUMBING-Rough | 11/4/2021 | Partial Approval | DAVID STEPANYAN |
| BUILDING-Rough-Frame | 11/30/2021 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 11/30/2021 | Corrections Issued | JAVIER RAMOS JR |
| PLUMBING-Rough | 11/30/2021 | Approved | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 12/16/2021 | Approved | JAVIER RAMOS JR |
| HVAC-Rough | 12/16/2021 | Approved | JAVIER RAMOS JR |
| Insulation | 12/16/2021 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 12/16/2021 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 12/29/2021 | Approved | JAVIER RAMOS JR |
| Drywall Nailing | 1/5/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Rough | 1/26/2022 | Approved | PETER FOLLING |
| Interior/Exterior Lathing | 1/26/2022 | Partial Approval | PETER FOLLING |
| Underground Mechanical | 1/26/2022 | Approved | PETER FOLLING |
| Final | 4/11/2022 | Corrections Issued | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 4/11/2022 | SGSOV Not Ready | JUSTIN HAWLEY |
| Smoke Detectors | 4/11/2022 | Approved | JUSTIN HAWLEY |
| Final | 4/20/2022 | Corrections Issued | CHRIS CHRISTENSEN |
| SGSOV-Seismic Gas S/O Valve | 4/20/2022 | SGSOV Approved | CHRIS CHRISTENSEN |
| Final | 4/26/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 5/5/2022 | Not Ready for Inspection | CHRIS CHRISTENSEN |
| Final | 5/13/2022 | OK to Issue CofO | CHRIS CHRISTENSEN |
| Service/Power Release | 5/13/2022 | Approved | CHRIS CHRISTENSEN |