7900 S LOYOLA BLVD 90045
Certificate Information: 7900 S LOYOLA BLVD 90045
- Application / Permit
- 21016-10000-10398
- Plan Check / Job No.
- B21LA07567
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Office
- Work Description
- INTERIOR-T.I. REMODEL (5159 S.F. TOTAL AREA-B & A3 OCCUPANCY) 1. NEW RESTROOMS, CORRIDOR, AND STORE ROOM (1330 SF) 2. UPGRADE FINISHES IN EXISTING MULTIPURPOSE ROOM (3315 SF) AND LOBBY (514 SF) 3. OPENING IN CONCRETE WALL EXTERIOR. EXTERIOR: 1. REPLACE 2 DOORS AND 4 WINDOWS. INFILL 1 WINDOW. 2. CONCRETE FLATWORK, RAMP AND STEPS (HCP UPGRADE) 3. ROOF EQUIPMENT.
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- Permit Finaled on 11/29/2021
Permit Application Status History
| Submitted | 4/23/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/6/2021 | SERGIO GUTIERREZ |
| Corrections Issued | 5/17/2021 | SERGIO GUTIERREZ |
| Quality Review Completed | 5/24/2021 | FARUK SEZER |
| Disabled Access Plans Picked Up | 6/2/2021 | APPLICANT |
| Green Plans Picked Up | 7/8/2021 | APPLICANT |
| Plan Check Approved | 8/20/2021 | SERGIO GUTIERREZ |
| Issued | 9/15/2021 | APPLICANT |
| Building Plans Picked Up | 9/17/2021 | APPLICANT |
| Permit Finaled | 11/24/2021 | DERRICK SPENCER |
Permit Application Clearance Information
| Green Code | Cleared | 7/8/2021 | AARON COSTA |
| Specific Plan | Cleared | 7/14/2021 | ESTHER AMAYA |
| Fire Marshal Fire Life Safety | Cleared | 7/20/2021 | ANDREW KO |
| DAS Clearance | Cleared | 8/5/2021 | SERGIO GUTIERREZ |
Contact Information
| Architect | , ; Lic. No.: C11673 | , |
| Contractor | T G Construction Inc; Lic. No.: 528058-B | 139 NEVADA ST EL SEGUNDO, CA 90245 |
| Engineer | Nagarajan,, Sivaram; Lic. No.: S6349 | 167 MATISSE CIRCLE ALISO VIEJO, CA 92656 |
Inspector Information
| DANIEL ARMENTA, (310) 914-3925 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Wood Frame | 9/17/2021 | Not Ready for Inspection | GRANT WOODS |
| Drywall Nailing | 9/23/2021 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 9/24/2021 | Conditional Approval | GRANT WOODS |
| Insulation | 9/24/2021 | Approved | DERRICK SPENCER |
| Deputy Drilled-In Anchors | 9/27/2021 | Conditional Approval | GRANT WOODS |
| Partition/T-Bar Ceiling | 10/4/2021 | Conditional Approval | GRANT WOODS |
| Footing/Foundation/Slab | 10/6/2021 | Approved | JOEY BUCHANAN |
| Deputy Reinf. Concrete | 10/7/2021 | Conditional Approval | GRANT WOODS |
| Partition/T-Bar Ceiling | 10/26/2021 | Conditional Approval | JOEY BUCHANAN |
| Partition/T-Bar Ceiling | 10/27/2021 | Not Ready for Inspection | GRANT WOODS |
| Final | 11/24/2021 | Permit Finaled | DERRICK SPENCER |
| Green Building Final | 11/24/2021 | Approved | DERRICK SPENCER |
| SGSOV-Seismic Gas S/O Valve | 11/24/2021 | SGSOV Approved | DERRICK SPENCER |
| Smoke Detectors | 11/24/2021 | Approved | DERRICK SPENCER |