1129 W 21ST ST 90731
Certificate Information: 1129 W 21ST ST 90731
- Application / Permit
- 21016-10000-10356
- Plan Check / Job No.
- B21LA07509
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2 OF 2 PROJECT ADDRESS: 1129-1131 W. 21ST ST. REMODEL REAR DUPLEX
- Permit Issued
- Issued on 8/19/2021
- Issuing Office
- Current Status
- Permit Finaled on 5/23/2023
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | JESSE VIDUYA |
| Corrections Issued | 6/8/2021 | JESSE VIDUYA |
| Quality Review Completed | 6/9/2021 | ALLEN MANALANSAN |
| Applicant returned to address corrections | 7/21/2021 | JESSE VIDUYA |
| Plan Check Approved | 8/4/2021 | JESSE VIDUYA |
| Issued | 8/19/2021 | APPLICANT |
| Building Plans Picked Up | 9/7/2021 | APPLICANT |
| Permit Finaled | 5/23/2023 | PAUL BECKER |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 8/3/2021 | BRIAN MILLER |
Contact Information
| Contractor | Lua Gustavo; Lic. No.: 989102-B | 21822 SEINE AVENUE HAWAIIAN GARDENS, CA 90716 |
Inspector Information
| KELLY WARNER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| PAUL BECKER, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| KEITH EDGHILL, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
| DANIEL GONZALEZ, (310) 732-4530 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/31/2021 | Corrections Issued | ANDREW BEELI |
| Footing/Foundation/Slab | 9/8/2021 | Corrections Issued | ANDREW BEELI |
| Rough-Elec/Plmb/HVAC | 7/12/2022 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 7/14/2022 | Approved | ANDREW BEELI |
| Insulation | 7/14/2022 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 7/14/2022 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Rough | 7/26/2022 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 7/26/2022 | Corrections Issued | ANDREW BEELI |
| BUILDING-Rough-Frame | 8/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| Drywall Nailing | 8/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| Final | 8/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 8/2/2022 | Not Ready for Inspection | ANDREW BEELI |
| Drywall Nailing | 8/16/2022 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 8/16/2022 | Not Ready for Inspection | ANDREW BEELI |
| Insulation | 8/16/2022 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 8/16/2022 | Partial Approval | ANDREW BEELI |
| BUILDING-Rough-Frame | 9/7/2022 | Approved | ANDREW BEELI |
| Drywall Nailing | 9/7/2022 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 9/7/2022 | Corrections Issued | ANDREW BEELI |
| Final | 9/7/2022 | Not Ready for Inspection | ANDREW BEELI |
| Insulation | 9/7/2022 | Partial Approval | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 9/7/2022 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 9/7/2022 | Partial Approval | ANDREW BEELI |
| Drywall Nailing | 9/13/2022 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Rough | 9/13/2022 | Approved | ANDREW BEELI |
| Drywall Nailing | 9/19/2022 | Corrections Issued | ANDREW BEELI |
| Drywall Nailing | 9/23/2022 | Corrections Issued | ANDREW BEELI |
| Drywall Nailing | 11/7/2022 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Rough | 11/7/2022 | Approved | ANDREW BEELI |
| Smoke Detectors | 11/7/2022 | Not Ready for Inspection | ANDREW BEELI |
| Drywall Nailing | 12/12/2022 | Approved | ANDREW BEELI |
| ELECTRICAL-Final | 12/12/2022 | Not Ready for Inspection | ANDREW BEELI |
| Final | 12/12/2022 | Not Ready for Inspection | ANDREW BEELI |
| HVAC-Final | 12/12/2022 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Final | 12/12/2022 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 12/12/2022 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 12/12/2022 | Not Ready for Inspection | ANDREW BEELI |
| Final | 12/14/2022 | Not Ready for Inspection | ANDREW BEELI |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Not Ready | ANDREW BEELI |
| Smoke Detectors | 12/14/2022 | Not Ready for Inspection | ANDREW BEELI |
| ELECTRICAL-Final | 1/27/2023 | Corrections Issued | ANDREW BEELI |
| HVAC-Final | 1/27/2023 | Not Ready for Inspection | ANDREW BEELI |
| PLUMBING-Final | 1/27/2023 | Corrections Issued | ANDREW BEELI |
| ELECTRICAL-Final | 3/23/2023 | Approved | PAUL BECKER |
| HVAC-Final | 3/23/2023 | Approved | PAUL BECKER |
| PLUMBING-Final | 3/23/2023 | Approved | PAUL BECKER |
| Final | 5/23/2023 | Permit Finaled | PAUL BECKER |
| SGSOV-Seismic Gas S/O Valve | 5/23/2023 | SGSOV Approved | PAUL BECKER |
| Smoke Detectors | 5/23/2023 | Approved | PAUL BECKER |