4707 W PINAFORE ST 90008
Certificate Information: 4707 W PINAFORE ST 90008
- Application / Permit
- 21016-10000-10306
- Plan Check / Job No.
- B21LA07479
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- Eplan: 22669 Soft-Story seismic retrofit per LABC Chapter 93: (1) new steel special cant. column
- Permit Issued
- Issued on 9/15/2021
- Issuing Office
- Current Status
- CofC Issued on 6/22/2022
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | JESSE VIDUYA |
| Corrections Issued | 5/10/2021 | JESSE VIDUYA |
| Quality Review Completed | 5/13/2021 | HANS SANTIAGO |
| Plan Check Approved | 6/2/2021 | JESSE VIDUYA |
| Issued | 9/15/2021 | APPLICANT |
| OK for CofC | 5/10/2022 | DARRYL ARNOLD |
| CofC Issued | 6/22/2022 | WINSTON DUNNING |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 9/1/2021 | RICARDO BOHORQUEZ |
Contact Information
| Contractor | Sater Development Strategies Inc; Lic. No.: 1074535-B | 9854 NATIONAL BLVD #235 LOS ANGELES, CA 90034 |
| Engineer | Alexander,, Andy Joseph; Lic. No.: C84086 | 1615 GRAMERCY AVE TORRANCE, CA 90501 |
Inspector Information
| DARRYL ARNOLD, (213) 482-0341 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 10/1/2021 | Conditional Approval | BRUCE CAMPBELL |
| Deputy Steel/Welding | 10/4/2021 | Conditional Approval | MARK FERRARI |
| Pre-Inspection | 10/4/2021 | Corrections Issued | DARRYL ARNOLD |
| Excavation/Setback/Form/Re-Bar | 10/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 10/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Structural Steel Frame | 10/8/2021 | Conditional Approval | DARRYL ARNOLD |
| Wood Frame | 10/8/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| Interior/Exterior Lathing | 10/15/2021 | Conditional Approval | DARRYL ARNOLD |
| Final | 12/27/2021 | Not Ready for Inspection | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 12/27/2021 | SGSOV Not Ready | DARRYL ARNOLD |
| Smoke Detectors | 12/27/2021 | Corrections Issued | DARRYL ARNOLD |
| Final | 5/10/2022 | OK for CofC | DARRYL ARNOLD |
| SGSOV-Seismic Gas S/O Valve | 5/10/2022 | SGSOV Approved | DARRYL ARNOLD |
| Smoke Detectors | 5/10/2022 | Approved | DARRYL ARNOLD |