8160 E REDLANDS ST 90293
Certificate Information: 8160 E REDLANDS ST 90293
- Application / Permit
- 21016-10000-10293
- Plan Check / Job No.
- B21LA07472
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- SOFT STORY RETROFIT AS PER LABC CH. 93. INSTALL 7 NEW SPECIAL STEEL CANTILEVER COLUMNS AND NEW WOOD SHEAR WALLS.
- Permit Issued
- Issued on 6/30/2021
- Issuing Office
- Current Status
- CofC Issued on 11/17/2021
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | HANS SANTIAGO |
| Corrections Issued | 5/4/2021 | HANS SANTIAGO |
| Quality Review Completed | 5/6/2021 | SAI KHUM |
| Building Plans Picked Up | 5/10/2021 | APPLICANT |
| Applicant returned to address corrections | 5/27/2021 | HANS SANTIAGO |
| Plan Check Approved | 6/2/2021 | ANDREW SANTIAGO |
| Issued | 6/30/2021 | APPLICANT |
| OK for CofC | 11/12/2021 | JOEY BUCHANAN |
| CofC Issued | 11/17/2021 | NICK LAROCCA |
Permit Application Clearance Information
| Tenant Habitability Plan | Cleared | 6/21/2021 | ISMAEL HERNANDEZ |
Contact Information
| Contractor | A M A Construction Services Inc; Lic. No.: 831856-B | 536 W ARROW HWY SUITE 201 COVINA, CA 91722 |
| Engineer | El-Mustapha,, Ahmad Mahmoud; Lic. No.: C49021 | 1608 CALLE CRISTINA SAN DIMAS, CA 91773 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/9/2021 | Approved | GRANT WOODS |
| Deputy Steel/Welding | 9/17/2021 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 9/21/2021 | Conditional Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 9/22/2021 | Conditional Approval | GRANT WOODS |
| Excavation/Setback/Form/Re-Bar | 9/23/2021 | Approved | DERRICK SPENCER |
| Structural Steel Frame | 9/23/2021 | Approved | DERRICK SPENCER |
| Wood Frame | 9/23/2021 | Approved | DERRICK SPENCER |
| Interior/Exterior Lathing | 9/29/2021 | Partial Approval | GRANT WOODS |
| Deputy Drilled-In Anchors | 10/4/2021 | Conditional Approval | GRANT WOODS |
| Deputy Wood Construction | 10/5/2021 | Approved | JOEY BUCHANAN |
| Deputy Wood Construction | 10/6/2021 | Approved | GRANT WOODS |
| Insulation | 10/6/2021 | Approved | GRANT WOODS |
| Wood Frame | 10/6/2021 | Partial Approval | GRANT WOODS |
| Deputy Wood Construction | 10/7/2021 | Conditional Approval | ALAN NOVAK |
| Floor/Roof Diaphrgm/Shear Wall | 10/8/2021 | Approved | GRANT WOODS |
| Interior/Exterior Lathing | 10/13/2021 | Approved | ALAN NOVAK |
| Final | 11/12/2021 | OK for CofC | JOEY BUCHANAN |
| METHANE-Final | 11/12/2021 | Approved | JOEY BUCHANAN |
| SGSOV-Seismic Gas S/O Valve | 11/12/2021 | SGSOV Approved | JOEY BUCHANAN |
| Smoke Detectors | 11/12/2021 | Approved | JOEY BUCHANAN |