2802 N DEEP CANYON DR 90210

Certificate Information: 2802 N DEEP CANYON DR 90210

Application / Permit
21016-10000-10236
Plan Check / Job No.
B21LA07424
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE SOME INTERIOR WALLS, REPLACE WINDOWS, AND DOORS WITH EXACT SIZE, ADD RESIDENTIAL ELEVATOR, REPLACE EXTERIOR GUARDRAILS
Permit Issued
Issued on 10/25/2021
Issuing Office
Current Status
Permit Finaled on 10/13/2023

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 5/25/2021 ZAW HAN
Corrections Issued 6/1/2021 ZAW HAN
Quality Review Completed 6/3/2021 KEN GILL
Applicant returned to address corrections 9/15/2021 ZAW HAN
Plan Check Approved 9/16/2021 ZAW HAN
Issued 10/25/2021 APPLICANT
Building Plans Picked Up 10/26/2021 APPLICANT
Permit Finaled 10/13/2023 ARAM AVEDISIAN

Permit Application Clearance Information

CPC Cleared 7/14/2021 RICHARD REASER
Specific Plan Cleared 7/14/2021 RICHARD REASER
ZA Case Cleared 7/14/2021 RICHARD REASER
Grading Pre-Inspection Cleared 9/16/2021 ALEXANDER HELFER

Contact Information

Architect Armandpour,, Bijan; Lic. No.: C15034 109 SIERRA STREET      EL SEGUNDO, CA 90245
Contractor Owner-Builder       ,
Engineer Guivatchian,, Mohammad; Lic. No.: C36510 4720 DEGOVIA AVENUE      WOODLAND HILLS, CA 91364

Inspector Information

CARLOS MATAMOROS, (310) 914-3878 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 3/21/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/21/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Footing/Foundation/Slab 3/22/2022 Conditional Approval GERMAN RODRIGUEZ MENDOZA
Special/Order Compliance 3/22/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
Wood Frame 3/22/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 4/18/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Rough 4/18/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
HVAC-Rough 4/18/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
PLUMBING-Rough 4/18/2022 Not Ready for Inspection GERMAN RODRIGUEZ MENDOZA
BUILDING-Rough-Frame 6/10/2022 Approved GERMAN RODRIGUEZ MENDOZA
Rough-Elec/Plmb/HVAC 6/10/2022 Approved GERMAN RODRIGUEZ MENDOZA
Final 10/13/2023 Permit Finaled ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 10/13/2023 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 10/13/2023 Approved ARAM AVEDISIAN