4923 N HESPERIA AVE 91316
Certificate Information: 4923 N HESPERIA AVE 91316
- Application / Permit
- 21016-10000-10120
- Plan Check / Job No.
- B21LA07337
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- Conversion of an (E) detached garage into an ADU per ordinance 186,481.
- Permit Issued
- Issued on 12/21/2021
- Issuing Office
- Current Status
- CofO Issued on 2/18/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/23/2021 | HELEN NGUYEN |
| Corrections Issued | 4/23/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/5/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 5/12/2021 | HELEN NGUYEN |
| Applicant returned to address corrections | 10/26/2021 | HELEN NGUYEN |
| Plan Check Approved | 12/9/2021 | HELEN NGUYEN |
| Issued | 12/21/2021 | APPLICANT |
| CofO in Progress | 10/11/2022 | DAVID SANDOVAL |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
| CofO Issued | 2/18/2023 | DANIEL ORRANTE |
| Permit Finaled | 2/18/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 5/3/2021 | GABRIEL ROBLES |
| Roof/Waste drainage to street | Cleared | 5/3/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/5/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/5/2021 | GABRIEL ROBLES |
| Grading Pre-Inspection | Cleared | 10/26/2021 | HELEN NGUYEN |
Contact Information
| Contractor | L A General Construction Co; Lic. No.: 1052200-B | 319 N CURTIS AVE APT A ALHAMBRA, CA 91801 |
Inspector Information
| JOHN KIDWELL, (818) 774-4314 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2022 | Corrections Issued | PETER FOLLING |
| PLUMBING-Rough | 3/16/2022 | Corrections Issued | PETER FOLLING |
| Footing/Foundation/Slab | 3/21/2022 | Corrections Issued | DAVID SANDOVAL |
| PLUMBING-Rough | 3/21/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Rough | 5/26/2022 | Approved | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/15/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 6/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 6/24/2022 | Approved | DAVID SANDOVAL |
| Green Building Rough | 6/24/2022 | Approved | DAVID SANDOVAL |
| Interior/Exterior Lathing | 6/24/2022 | Partial Approval | DAVID SANDOVAL |
| Rough-Elec/Plmb/HVAC | 6/24/2022 | Approved | DAVID SANDOVAL |
| Insulation | 7/1/2022 | Approved | MORRIS JACKSON |
| Drywall Nailing | 7/8/2022 | Approved | MICHAEL SMITH |
| Shower Pan | 7/12/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 9/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Final | 9/15/2022 | Corrections Issued | DAVID SANDOVAL |
| Green Building Final | 9/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| HVAC-Final | 9/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| PLUMBING-Final | 9/15/2022 | Not Ready for Inspection | DAVID SANDOVAL |
| Smoke Detectors | 9/15/2022 | Approved | DAVID SANDOVAL |
| Final | 9/29/2022 | Not Ready for Inspection | DAVID SCANTLIN |
| Green Building Final | 9/29/2022 | Approved | DAVID SCANTLIN |
| ELECTRICAL-Final | 10/7/2022 | Approved | DAVID SANDOVAL |
| Final | 10/7/2022 | OK to Issue CofO | DAVID SANDOVAL |
| HVAC-Final | 10/7/2022 | Approved | DAVID SANDOVAL |
| PLUMBING-Final | 10/7/2022 | Approved | DAVID SANDOVAL |