8114 N LURLINE AVE 91306
Certificate Information: 8114 N LURLINE AVE 91306
- Application / Permit
- 21016-10000-10092
- Plan Check / Job No.
- B21LA07326
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- INTERIOR REMODELING OF (E) BEDROOM, BATHROOM, LIVING ROOM AND KITCHEN.
- Permit Issued
- Issued on 6/3/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/17/2021
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/21/2021 | FARSHAD ALIMOHAMADI |
| Corrections Issued | 4/22/2021 | FARSHAD ALIMOHAMADI |
| Building Plans Picked Up | 4/23/2021 | APPLICANT |
| Plan Check Approved | 5/10/2021 | RICARDO RAMIREZ |
| Issued | 6/3/2021 | APPLICANT |
| Permit Finaled | 12/17/2021 | STEVEN BACK |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Wassef,, Mena Maher Salama; Lic. No.: C84979 | 28131 VALERIO CT VALENCIA, CA 91354 |
Inspector Information
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/9/2021 | Approved | HENRY KIM |
| Footing/Foundation/Slab | 7/26/2021 | Approved | HENRY KIM |
| PLUMBING-Rough | 7/26/2021 | Corrections Issued | HENRY KIM |
| Deputy Drilled-In Anchors | 7/28/2021 | Conditional Approval | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 8/14/2021 | Approved | STEVEN BACK |
| HVAC-Rough | 8/14/2021 | Not Ready for Inspection | STEVEN BACK |
| PLUMBING-Rough | 8/14/2021 | Approved | STEVEN BACK |
| Wood Frame | 8/14/2021 | Corrections Issued | STEVEN BACK |
| BUILDING-Rough-Frame | 8/20/2021 | Corrections Issued | HENRY KIM |
| HVAC-Rough | 8/20/2021 | Corrections Issued | HENRY KIM |
| Shower Pan | 8/20/2021 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 8/27/2021 | Partial Approval | HENRY KIM |
| Interior/Exterior Lathing | 8/27/2021 | Approved | HENRY KIM |
| Drywall Nailing | 9/7/2021 | Partial Approval | HENRY KIM |
| Floor/Roof Diaphrgm/Shear Wall | 9/7/2021 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 9/7/2021 | Approved | HENRY KIM |
| Drywall Nailing | 9/10/2021 | Approved | DEANDRE HOFFMAN |
| Final | 12/3/2021 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Not Ready | STEPHANIE SWANSON |
| Smoke Detectors | 12/3/2021 | Approved | STEPHANIE SWANSON |
| Final | 12/17/2021 | Permit Finaled | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 12/17/2021 | SGSOV Gas Company | STEVEN BACK |