522 N MERIDIAN TER 90042

Certificate Information: 522 N MERIDIAN TER 90042

Application / Permit
21016-10000-10032
Plan Check / Job No.
B21LA07297
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT 2 CAR GARAGE AND RECREATION ROOM TO ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A); ALL WORK PER WFPP
Permit Issued
Issued on 8/9/2021
Issuing Office
Current Status
CofO Issued on 3/11/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/21/2021 APPLICANT
Assigned to Plan Check Engineer 4/26/2021 SINA KHOSRAVI
Corrections Issued 4/27/2021 SINA KHOSRAVI
Applicant returned to address corrections 5/26/2021 RAHEL BEYENE
Applicant returned to address corrections 7/22/2021 CARLOS MONTES
Plan Check Approved 8/4/2021 SHANGQIN XIE
Issued 8/9/2021 APPLICANT
Building Plans Picked Up 8/11/2021 APPLICANT
CofO in Progress 3/2/2022 CRAIG VAUGHAN
CofO in Progress 3/2/2022 CRAIG VAUGHAN
Permit Finaled 3/11/2022 DEROLD HAUFF
CofO Issued 3/11/2022 DEROLD HAUFF
Permit Finaled 3/11/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 5/18/2021 CELINA MORENO
Sewer availability Cleared 5/18/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 5/20/2021 CELINA MORENO
Grading Pre-Inspection Cleared 6/16/2021 PATRICK MISCHLICH

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/16/2021 Partial Inspection CRAIG VAUGHAN
Footing/Foundation/Slab 9/13/2021 Corrections Issued CRAIG VAUGHAN
Footing/Foundation/Slab 9/15/2021 Not Ready for Inspection CRAIG VAUGHAN
Sewer 9/15/2021 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 9/17/2021 Approved CRAIG VAUGHAN
Wood Frame 9/24/2021 Not Ready for Inspection CRAIG VAUGHAN
PLUMBING-Rough 9/28/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Wood Frame 9/28/2021 Not Ready for Inspection HAMIK HARTOUNIAN
Rough-Elec/Plmb/HVAC 10/12/2021 Not Ready for Inspection CRAIG DAVIS
Wood Frame 10/12/2021 Not Ready for Inspection CRAIG DAVIS
Rough-Elec/Plmb/HVAC 10/21/2021 Corrections Issued CRAIG VAUGHAN
Wood Frame 10/21/2021 Approved CRAIG VAUGHAN
Rough-Elec/Plmb/HVAC 11/19/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 11/24/2021 Corrections Issued CRAIG VAUGHAN
Gas Test 11/24/2021 Not Ready for Inspection CRAIG VAUGHAN
Insulation 11/24/2021 Approved CRAIG VAUGHAN
Wood Frame 11/24/2021 Partial Approval CRAIG VAUGHAN
ELECTRICAL-Rough 12/1/2021 Approved CRAIG VAUGHAN
Gas Test 12/1/2021 Approved CRAIG VAUGHAN
Insulation 12/1/2021 Approved CRAIG VAUGHAN
Wood Frame 12/1/2021 Approved CRAIG VAUGHAN
ELECTRICAL-Final 12/13/2021 Not Ready for Inspection CRAIG VAUGHAN
ELECTRICAL-Final 12/27/2021 Not Ready for Inspection HAMIK HARTOUNIAN
BUILDING-Rough-Frame 1/27/2022 Approved CRAIG VAUGHAN
Final 1/27/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 1/27/2022 SGSOV Not Ready CRAIG VAUGHAN
Smoke Detectors 1/27/2022 Approved CRAIG VAUGHAN
Final 2/24/2022 Corrections Issued CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 2/24/2022 SGSOV Approved CRAIG VAUGHAN
ELECTRICAL-Final 3/1/2022 Approved CRAIG VAUGHAN
Final 3/1/2022 OK to Issue CofO CRAIG VAUGHAN
HVAC-Final 3/1/2022 Approved CRAIG VAUGHAN
PLUMBING-Final 3/1/2022 Approved CRAIG VAUGHAN