4429 S VERMONT AVE 90037
Certificate Information: 4429 S VERMONT AVE 90037
- Application / Permit
- 21016-10000-10018
- Plan Check / Job No.
- B21LA07287
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 5 STORY 34 UNITS (4 ELI = 11%) AFFORDABLE HOUSING APARTMENT TO INCLUDE 4 STORIES OF TYPE VA APARTMENT OVER 1 STORY TYPE IA PARKING, TIER 3 TOC WITH ADDITIONAL INCENTIVE.
- Permit Issued
- Issued on 10/18/2024
- Issuing Office
- Metro
- Current Status
- Issued on 10/18/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Plan Check Approved | 2/21/2024 | KEVIN MORALES |
| Issued | 10/18/2024 | APPLICANT |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/17/2021 | CECILIO NAVARRO |
| Address approval | Cleared | 5/19/2021 | CECILIO NAVARRO |
| Community Plan Implem. Overlay | Cleared | 5/19/2021 | CECILIO NAVARRO |
| Community Plan Implem. Overlay | Cleared | 5/29/2021 | WALTER RAMIREZ |
| Community Plan Implem. Overlay | Cleared | 8/10/2021 | JOHN KIM |
| Trees in Parkway | Cleared | 9/2/2021 | JOHN KIM |
| Green Code | Cleared | 8/4/2022 | MICHAEL AYERS |
| Hydrant and Access approval | Cleared | 9/8/2022 | MATTHEW CRAIG |
| Fire Marshal Fire Life Safety | Cleared | 11/3/2022 | RONILO MULAWIN |
| Historic Resource Verification | Cleared | 2/6/2023 | MAX LODER |
| Community Plan Implem. Overlay | Cleared | 2/16/2023 | COLLINS ALLAN |
| Sewer availability | Cleared | 4/14/2023 | STEVE MELGAR |
| Density Bonus 12.22.A.31 | Cleared | 5/18/2023 | JAMES MCCARTHY |
| "D" conditions | Cleared | 6/7/2023 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 6/7/2023 | RAFAEL FONTES |
| Community Plan Implem. Overlay | Cleared | 6/7/2023 | RAFAEL FONTES |
| Low Impact Development | Cleared | 6/16/2023 | JORGE MEJIA LEMUS |
| Miscellaneous | Cleared | 7/18/2023 | SPENCER WEJROWSKI |
| Miscellaneous | Cleared | 7/18/2023 | SPENCER WEJROWSKI |
| Opn space landscape/Water mgmt | Cleared | 7/18/2023 | SPENCER WEJROWSKI |
| Roof/Waste drainage to street | Cleared | 7/25/2023 | TERRY PHAN |
| Redevelopment Project Area | Cleared | 7/27/2023 | SUSAN WONG |
| Work Adjacent to Public Way | Cleared | 9/27/2023 | LARRY LEE |
| Highway dedication | Cleared | 11/7/2023 | TERRY PHAN |
| DAS Clearance | Cleared | 11/14/2023 | KEVIN MORALES |
| Building over 36-ft | Cleared | 12/12/2023 | CALOSHA APPROVED |
Contact Information
| Contractor | Mike Mohrsaz; Lic. No.: 910443-B | 5080 AVENIDA HACIENDA TARZANA, CA 91356 |
| Engineer | Koma,, Shahram Javadi; Lic. No.: C69497 | 23241 VENTURA BLVD 300 WOODLAND HILLS, CA 91364 |
Inspector Information
| PAUL BAZERKANIAN, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| LUIS CCAMACHO, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN MORELOS, (213) 482-0353 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 12/27/2024 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 12/27/2024 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 1/7/2025 | Partial Approval | ALFREDO LOPEZ |
| Reinforced Masonry Frame | 1/21/2025 | Partial Approval | ALFREDO LOPEZ |
| Masonry Wall/Backfill | 1/23/2025 | Approved | DARRYL ARNOLD |
| Masonry Wall/Backfill | 2/4/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Masonry Wall/Backfill | 2/6/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Reinforced Concrete Frame | 2/6/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Reinforced Masonry Frame | 2/6/2025 | Not Ready for Inspection | ALFREDO LOPEZ |
| Excavation/Setback/Form/Re-Bar | 2/7/2025 | Partial Approval | ALFREDO LOPEZ |
| Deputy Shotcrete | 2/10/2025 | Partial Approval | JAMES POWERS |
| Deputy Shotcrete | 2/11/2025 | Partial Approval | ALFREDO LOPEZ |
| Masonry Wall/Backfill | 2/11/2025 | Conditional Approval | DARRYL ARNOLD |
| Footing/Foundation/Slab | 3/25/2025 | Conditional Approval | DARRYL ARNOLD |
| Reinforced Concrete Frame | 4/25/2025 | Approved | DARRYL ARNOLD |
| Footing/Foundation/Slab | 5/7/2025 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/28/2025 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 6/9/2025 | Conditional Approval | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2025 | Partial Approval | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/24/2025 | Partial Approval | ALFREDO LOPEZ |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2025 | Approved | DARRYL ARNOLD |
| Deputy Wood Construction | 7/30/2025 | Partial Approval | JAMES POWERS |
| Insulation | 8/12/2025 | Approved | DARRYL ARNOLD |
| Floor/Roof Diaphrgm/Shear Wall | 8/19/2025 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 8/25/2025 | Partial Approval | ALFREDO LOPEZ |
| Special/Order Compliance | 9/4/2025 | Corrections Issued | ALFREDO LOPEZ |
| Insulation | 9/9/2025 | Partial Approval | ALFREDO LOPEZ |
| Insulation | 9/17/2025 | Approved | DARRYL ARNOLD |
| Drywall Nailing | 9/22/2025 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2025 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 10/8/2025 | Partial Approval | ALFREDO LOPEZ |
| Wood Frame | 10/15/2025 | Corrections Issued | ALFREDO LOPEZ |
| Insulation | 10/21/2025 | Conditional Approval | DARRYL ARNOLD |
| Drywall Nailing | 10/28/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 11/3/2025 | Partial Approval | ALFREDO LOPEZ |
| Drywall Nailing | 11/12/2025 | Partial Approval | ALFREDO LOPEZ |
| Light Gage Steel Frame | 12/2/2025 | Approved | DARRYL ARNOLD |
| Pre-Inspection | 1/5/2026 | Partial Inspection | ALFREDO LOPEZ |
| Light Gage Steel Frame | 5/4/2026 | Approved | DARRYL ARNOLD |