1118 S HIGHLAND AVE 90019
Certificate Information: 1118 S HIGHLAND AVE 90019
- Application / Permit
- 21016-10000-09875
- Plan Check / Job No.
- B21LA07175
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 2-STORY REC. ROOM CONVERSION TO ACCESSORY DWELLING UNIT W/ ATTACHED CARPORT.
- Permit Issued
- Issued on 3/7/2022
- Issuing Office
- Current Status
- CofO Issued on 12/17/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/26/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 4/26/2021 | SAMUEL GONZALEZ |
| Applicant returned to address corrections | 11/18/2021 | JOSEPH RAFOLS |
| Applicant returned to address corrections | 1/12/2022 | RICARDO RAMIREZ |
| Plan Check Approved | 2/9/2022 | FERNANDO FLORES |
| Issued | 3/7/2022 | APPLICANT |
| Building Plans Picked Up | 3/9/2022 | APPLICANT |
| CofO in Progress | 12/12/2022 | MICHAEL LEWIS |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
| CofO Issued | 12/17/2022 | DEROLD HAUFF |
| Permit Finaled | 12/17/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/11/2021 | CECILIO NAVARRO |
| Eng Process Fee Ord 176,300 | Cleared | 6/11/2021 | CECILIO NAVARRO |
| Sewer availability | Cleared | 6/11/2021 | CECILIO NAVARRO |
| Construction near power lines | Cleared | 8/2/2021 | RIDWAN HARDY |
Contact Information
| Contractor | Grenier Construction; Lic. No.: 636045-B | 22643 COVELLO STREET WEST HILLS, CA 91307 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| ELECTRICAL-Rough | 6/3/2022 | Corrections Issued | ADAM ESCOTO |
| PLUMBING-Rough | 6/3/2022 | Corrections Issued | ADAM ESCOTO |
| BUILDING-Rough-Frame | 6/9/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Rough | 6/9/2022 | Approved | ADAM ESCOTO |
| METHANE-Rough | 6/9/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Rough | 6/9/2022 | Approved | ADAM ESCOTO |
| ELECTRICAL-Final | 7/27/2022 | Approved | ADAM ESCOTO |
| Final | 7/27/2022 | Corrections Issued | ADAM ESCOTO |
| Footing/Foundation/Slab | 7/27/2022 | Approved | ADAM ESCOTO |
| HVAC-Final | 7/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| METHANE-Barrier | 7/27/2022 | Approved | ADAM ESCOTO |
| METHANE-Subgrade | 7/27/2022 | Approved | ADAM ESCOTO |
| PLUMBING-Final | 7/27/2022 | Approved | ADAM ESCOTO |
| SGSOV-Seismic Gas S/O Valve | 7/27/2022 | SGSOV Not Ready | ADAM ESCOTO |
| Smoke Detectors | 7/27/2022 | Not Ready for Inspection | ADAM ESCOTO |
| Final | 8/17/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/17/2022 | SGSOV Not Ready | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/17/2022 | Approved | ALIZAH MAYAGOITIA |
| Final | 12/9/2022 | OK to Issue CofO | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Approved | MICHAEL LEWIS |