247 N DELFERN DR 90077
Certificate Information: 247 N DELFERN DR 90077
- Application / Permit
- 21016-10000-09537
- Plan Check / Job No.
- B21LA06962
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW ACCESSORY DWELLING UNIT WITH CABANA ON TOP.
- Permit Issued
- Issued on 5/10/2023
- Issuing Office
- Valley
- Current Status
- Issued on 5/10/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | ERIC WONG |
| Corrections Issued | 4/28/2021 | ERIC WONG |
| Quality Review Completed | 5/5/2021 | PETER KIM |
| Building Plans Picked Up | 5/7/2021 | APPLICANT |
| Applicant returned to address corrections | 4/20/2022 | ERIC WONG |
| Applicant returned to address corrections | 5/26/2022 | ERIC WONG |
| Applicant returned to address corrections | 6/3/2022 | ERIC WONG |
| Applicant returned to address corrections | 7/11/2022 | ERIC WONG |
| Applicant returned to address corrections | 7/19/2022 | ERIC WONG |
| Applicant returned to address corrections | 10/14/2022 | ERIC WONG |
| Applicant returned to address corrections | 12/16/2022 | ERIC WONG |
| Plan Check Approved | 4/13/2023 | ERIC WONG |
| Issued | 5/10/2023 | APPLICANT |
Permit Application Clearance Information
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| BHO/Hillside ordinance | Cleared | 10/28/2021 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 11/1/2021 | DINAH GARIN |
| Sewer availability | Cleared | 11/4/2021 | DINAH GARIN |
| Address approval | Cleared | 6/29/2022 | JENSON LEE |
| Hydrant and Access approval | Cleared | 9/26/2022 | KURT CORRAL |
| Grading Pre-Inspection | Cleared | 10/7/2022 | ERIC WONG |
| ZI | Cleared | 3/23/2023 | RUBEN VASQUEZ |
| Roof/Waste drainage to street | Cleared | 3/24/2023 | JENSON LEE |
| Certificate of Compliance | Cleared | 4/5/2023 | MARC WOERSCHING |
| Low Impact Development | Cleared | 4/13/2023 | ORVAL HERNANDEZ-MARCI |
Contact Information
| Architect | Harouni,, Faradj-Ollah; Lic. No.: C13577 | 6334 WILSHIRE BLVD LOS ANGELES, CA 90048 |
| Contractor | Calcon Construction Inc; Lic. No.: 761177-B | 2001 S BARRINGT6ON AVE STE 201-A LOS ANGELES, CA 90025 |
| Engineer | Berkoz,, Ertunga; Lic. No.: S2504 | 4665 ELLENITA AVE TARZANA, CA 91356 |
Inspector Information
| RYAN SALAZAR, (310) 914-3862 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Piling/Pier/Caisson | 4/22/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 4/25/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Piling/Pier/Caisson | 4/29/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Grading | 5/1/2024 | Conditional Approval | MICHAEL PELHAM |
| Piling/Pier/Caisson | 5/14/2024 | Partial Approval | SEAN HAUPT |
| PLUMBING-Rough | 5/24/2024 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/2/2024 | Not Ready for Inspection | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/8/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 7/23/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 7/26/2024 | Partial Approval | CHRISTOPHER WILSON |
| Reinforced Concrete Frame | 7/26/2024 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 7/29/2024 | Conditional Approval | CHRISTOPHER WILSON |
| Deputy Shotcrete | 7/29/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Shotcrete | 8/1/2024 | Conditional Approval | CHRISTOPHER WILSON |
| PLUMBING-Rough | 8/15/2024 | Partial Approval | ARAM AVEDISIAN |
| Deputy Reinf. Concrete | 8/21/2024 | Conditional Approval | MICHAEL PELHAM |
| Footing/Foundation/Slab | 8/22/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Masonry | 8/28/2024 | Conditional Approval | MICHAEL PELHAM |
| Reinforced Masonry Frame | 8/28/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Masonry | 8/29/2024 | Conditional Approval | MICHAEL PELHAM |
| Deputy Reinf. Masonry | 9/3/2024 | Conditional Approval | MICHAEL PELHAM |
| Reinforced Masonry Frame | 9/4/2024 | Partial Approval | SEAN HAUPT |
| Deputy Reinf. Concrete | 9/17/2024 | Conditional Approval | MICHAEL PELHAM |
| Reinforced Concrete Frame | 9/18/2024 | Partial Approval | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 11/21/2024 | Approved | CHRISTOPHER WILSON |
| Sewer | 6/2/2026 | Approved | RYAN SALAZAR |