18480 S NEW HAMPSHIRE AVE 90248

Certificate Information: 18480 S NEW HAMPSHIRE AVE 90248

Application / Permit
21016-10000-09277
Plan Check / Job No.
B20LA24434
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert existing detached garage to ADU & add to ADU (1-STORY) PER ORDINANCE
Permit Issued
Issued on 8/30/2022
Issuing Office
Current Status
CofO Issued on 5/9/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2021 APPLICANT
Assigned to Plan Check Engineer 5/13/2021 CARLOS MONTES
Corrections Issued 5/14/2021 CARLOS MONTES
Quality Review Completed 5/20/2021 WING SUEN
Applicant returned to address corrections 9/17/2021 CARLOS MONTES
Applicant returned to address corrections 10/20/2021 CARLOS MONTES
Applicant returned to address corrections 2/17/2022 CARLOS MONTES
Plan Check Approved 7/26/2022 CARLOS MONTES
Issued 8/30/2022 APPLICANT
CofO in Progress 3/20/2023 JAMES CHAVEZ
Permit Finaled 5/9/2023 DANIEL ORRANTE
CofO Issued 5/9/2023 DANIEL ORRANTE
Permit Finaled 5/9/2023 DANIEL ORRANTE

Permit Application Clearance Information

Construction within easement Cleared 1/5/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 2/23/2022 JOSE HERNANDEZ
Sewer availability Cleared 2/23/2022 JOSE HERNANDEZ
Roof/Waste drainage to street Cleared 6/3/2022 ERIK BEASLEY
Address approval Cleared 7/6/2022 ERIK BEASLEY
Encroachment in public way Cleared 7/21/2022 CHINH DINH

Contact Information

Contractor Savi Construction; Lic. No.: 1077231-B       ,
Engineer Poore,, Gates Morton; Lic. No.: C41511 3794 LUCY AVE      RENO, NV 89512

Inspector Information

BEN MOLSTAD, (310) 732-4557 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/15/2022 Approved JOHN KLARIN
Footing/Foundation/Slab 9/28/2022 Corrections Issued EUGENE CASSIDY
Footing/Foundation/Slab 10/20/2022 Corrections Issued ALIZAH MAYAGOITIA
BUILDING-Rough-Frame 12/1/2022 Not Ready for Inspection JOHN KLARIN
ELECTRICAL-Rough 12/1/2022 Not Ready for Inspection JOHN KLARIN
Green Building Rough 12/1/2022 Not Ready for Inspection JOHN KLARIN
MERV13>=Rough 12/1/2022 Not Ready for Inspection JOHN KLARIN
Wood Frame 12/1/2022 Corrections Issued JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 12/16/2022 Partial Approval EUGENE CASSIDY
Rough-Elec/Plmb/HVAC 12/16/2022 Not Ready for Inspection EUGENE CASSIDY
ELECTRICAL-Rough 12/22/2022 Corrections Issued JAMES CHAVEZ
PLUMBING-Rough 12/22/2022 Corrections Issued JAMES CHAVEZ
Drywall Nailing 12/23/2022 Approved JAMES CHAVEZ
Drywall Nailing 1/4/2023 Approved JAMES CHAVEZ
Interior/Exterior Lathing 1/10/2023 Approved JAMES CHAVEZ
BUILDING-Rough-Frame 2/23/2023 Approved JAMES CHAVEZ
Footing/Foundation/Slab 2/23/2023 Approved JAMES CHAVEZ
Green Building Rough 2/23/2023 Approved JAMES CHAVEZ
MERV13>=Final 2/23/2023 Approved JAMES CHAVEZ
MERV13>=Rough 2/23/2023 Approved JAMES CHAVEZ
Pre-Inspection 2/23/2023 Partial Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 2/23/2023 SGSOV Not Ready JAMES CHAVEZ
Final 3/6/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 3/6/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/6/2023 SGSOV Not Ready JAMES CHAVEZ
Smoke Detectors 3/6/2023 Corrections Issued JAMES CHAVEZ
ELECTRICAL-Final 3/15/2023 Corrections Issued JAMES CHAVEZ
Green Building Final 3/15/2023 Approved JAMES CHAVEZ
Grounding or Bonding 3/15/2023 Corrections Issued JAMES CHAVEZ
PLUMBING-Final 3/15/2023 Approved JAMES CHAVEZ
Smoke Detectors 3/15/2023 Approved JAMES CHAVEZ
Final 3/17/2023 OK to Issue CofO JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 3/17/2023 SGSOV Approved JAMES CHAVEZ