16652-16654 W JERSEY ST 91344
Certificate Information: 16652-16654 W JERSEY ST 91344
- Application / Permit
- 21016-10000-09193
- Plan Check / Job No.
- B21LA06774
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: Convert attached 2 car garage into Accessory dwelling unit per LAMC 12.22A.33(B)(5)
- Permit Issued
- Issued on 6/21/2021
- Issuing Office
- Current Status
- CofO Issued on 6/21/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/15/2021 | MONICA RAMIREZ |
| Corrections Issued | 4/15/2021 | MONICA RAMIREZ |
| Applicant returned to address corrections | 6/15/2021 | MONICA RAMIREZ |
| Plan Check Approved | 6/17/2021 | MONICA RAMIREZ |
| Issued | 6/21/2021 | APPLICANT |
| CofO in Progress | 5/25/2022 | JAVIER RAMOS JR |
| CofO Issued | 6/21/2022 | RONALD MYRICK |
| Permit Finaled | 6/21/2022 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 5/10/2021 | GABRIEL ROBLES |
| Eng Process Fee Ord 176,300 | Cleared | 5/10/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/10/2021 | GABRIEL ROBLES |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/12/2021 | Not Ready for Inspection | JOHN HAYES |
| Pre-Inspection | 8/20/2021 | Partial Inspection | MARK JOHNSON |
| PLUMBING-Rough | 9/14/2021 | Approved | MARK JOHNSON |
| Deputy Drilled-In Anchors | 9/17/2021 | Approved | MARK JOHNSON |
| Excavation/Setback/Form/Re-Bar | 9/17/2021 | Approved | MARK JOHNSON |
| Footing/Foundation/Slab | 9/17/2021 | Approved | MARK JOHNSON |
| PLUMBING-Rough | 12/14/2021 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/18/2022 | Approved | MARK JOHNSON |
| HVAC-Rough | 1/18/2022 | Partial Approval | MARK JOHNSON |
| PLUMBING-Rough | 1/18/2022 | Approved | MARK JOHNSON |
| Wood Frame | 1/18/2022 | Not Ready for Inspection | MARK JOHNSON |
| BUILDING-Rough-Frame | 1/27/2022 | Approved | MICHAEL TEMPLE |
| HVAC-Rough | 1/27/2022 | Approved | MICHAEL TEMPLE |
| Interior/Exterior Lathing | 1/27/2022 | Partial Approval | MICHAEL TEMPLE |
| Wood Frame | 1/27/2022 | Approved | MICHAEL TEMPLE |
| Insulation | 2/7/2022 | Conditional Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 2/22/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 4/18/2022 | Corrections Issued | RAUL OLAGI |
| Final | 4/18/2022 | Corrections Issued | RAUL OLAGI |
| HVAC-Final | 4/18/2022 | Corrections Issued | RAUL OLAGI |
| PLUMBING-Final | 4/18/2022 | Corrections Issued | RAUL OLAGI |
| SGSOV-Seismic Gas S/O Valve | 4/18/2022 | SGSOV Not Ready | RAUL OLAGI |
| Smoke Detectors | 4/18/2022 | Approved | RAUL OLAGI |
| Final | 4/29/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 4/29/2022 | SGSOV Approved | JAVIER RAMOS JR |
| Final | 5/16/2022 | Partial Approval | JAVIER RAMOS JR |
| Final | 5/25/2022 | Conditional Approval | JAVIER RAMOS JR |