516 N CITRUS AVE 90036

Certificate Information: 516 N CITRUS AVE 90036

Application / Permit
21016-10000-09161
Plan Check / Job No.
B21LA06744
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
INTERIOR BATHROOM AND KITCHEN REMODEL. ADD ADDITIONAL BATHROOM IN (E) CABANA IN REAR YARD. NO STRUCTURAL MODIFICATIONS.
Permit Issued
Issued on 4/28/2021
Issuing Office
Current Status
Permit Finaled on 2/10/2022

Permit Application Status History

Submitted 4/12/2021 APPLICANT
Assigned to Plan Check Engineer 4/14/2021 JOSEPH RAFOLS
Corrections Issued 4/14/2021 JOSEPH RAFOLS
Building Plans Picked Up 4/14/2021 APPLICANT
Plan Check Approved 4/28/2021 JOSEPH RAFOLS
Issued 4/28/2021 APPLICANT
Permit Finaled 2/9/2022 AMY COLIN

Permit Application Clearance Information

No Data Available.

Contact Information

Contractor Owner-Builder       ,

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Sewer 6/18/2021 Partial Approval RAUL BARAJAS
Rough-Elec/Plmb/HVAC 7/30/2021 Corrections Issued BRIAN SULLIVAN
ELECTRICAL-Rough 8/5/2021 Partial Approval RAUL BARAJAS
PLUMBING-Rough 8/6/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 10/8/2021 Approved DANIEL GONZALEZ
Interior/Exterior Lathing 10/8/2021 Partial Approval DANIEL GONZALEZ
HVAC-Rough 10/13/2021 Corrections Issued SCOTT FINNILA
Special/Order Compliance 10/13/2021 Corrections Issued SCOTT FINNILA
HVAC-Rough 10/20/2021 Partial Approval ARTHUR SARGSYAN
Insulation 10/22/2021 Partial Approval JOSEPH MCGARRY
Interior/Exterior Lathing 11/10/2021 Corrections Issued JOSEPH MCGARRY
Interior/Exterior Lathing 11/15/2021 Partial Approval CHRIS CHRISTENSEN
Shower Pan 11/15/2021 Approved CHRIS CHRISTENSEN
Final 2/9/2022 Permit Finaled AMY COLIN
SGSOV-Seismic Gas S/O Valve 2/9/2022 SGSOV Approved AMY COLIN
Smoke Detectors 2/9/2022 Approved AMY COLIN