22001 W VENTURA BLVD 91364

Certificate Information: 22001 W VENTURA BLVD 91364

Application / Permit
21016-10000-09104
Plan Check / Job No.
B21LA06686
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(16) Retail
Work Description
CHANGE OF USE FROM BANK TO GROCERY STORE TENANT FIT-OUT WITH (N) INTERIOR PARTITIONS, FINISHES, FIXTURES, EQUIPMENT AND RESTROOMS.
Permit Issued
Issued on 10/5/2021
Issuing Office
Current Status
CofO Issued on 2/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/13/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 SERGIO GUTIERREZ
Disabled Access Plans Picked Up 4/27/2021 APPLICANT
Corrections Issued 4/28/2021 SERGIO GUTIERREZ
Quality Review Completed 5/14/2021 FARUK SEZER
Plan Check Approved 8/20/2021 SERGIO GUTIERREZ
Building Plans Picked Up 8/24/2021 APPLICANT
Issued 10/5/2021 APPLICANT
TCO Issued (Expire Date: 05-06-2023) 11/7/2022 RICKEY JACKSON
CofO in Progress 1/27/2023 BRIAN KELLY
Permit Finaled 2/2/2023 JEFFREY DURAN
CofO Issued 2/2/2023 JEFFREY DURAN
Permit Finaled 2/2/2023 JEFFREY DURAN

Permit Application Clearance Information

Specific Plan Cleared 5/11/2021 BRANDON WILSON
Green Code Cleared 6/14/2021 SERGIO GUTIERREZ
Miscellaneous Cleared 6/21/2021 CORREY KITCHENS
Specific Plan Cleared 6/21/2021 CORREY KITCHENS
DAS Clearance Cleared 7/26/2021 SERGIO GUTIERREZ
Food establishment approval Cleared 8/20/2021 LACDHS APPROVED

Contact Information

Architect Meyer,, Mariah B; Lic. No.: C37440 8131 METCALF, SUITE 300      OVERLAND PARK, KS 66204
Contractor Fulcrum Construction Inc; Lic. No.: 832993-B 13450 MAXELLA AVE STE 225      MARINA DEL REY, CA 90292
Engineer Habliston,, Alex Douglas; Lic. No.: S6694 13328 NE 20TH ST STE 100      BELLEVUE, WA 98005

Inspector Information

BRIAN KELLY, (818) 374-1127 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/12/2021 Conditional Approval PAUL DAVIDSON
Deputy Drilled-In Anchors 11/16/2021 Conditional Approval DANIEL VARNUM
Deputy Reinf. Concrete 11/16/2021 Conditional Approval DANIEL VARNUM
Structural Steel Frame 12/15/2021 Partial Approval CAMERON CHABAN
Wall Anchors 12/15/2021 Partial Approval CAMERON CHABAN
Light Gage Steel Frame 1/5/2022 Partial Approval ANDREW DORSO
Drywall Nailing 1/25/2022 Approved DANIEL VARNUM
Drywall Nailing 2/11/2022 Approved CAMERON CHABAN
Light Gage Steel Frame 2/11/2022 Approved CAMERON CHABAN
T-Bar Ceiling 8/9/2022 Not Ready for Inspection DANIEL VARNUM
T-Bar Ceiling 8/30/2022 Approved CAMERON CHABAN
Deputy Reinf. Concrete 9/13/2022 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 9/20/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 9/21/2022 Approved DANIEL VARNUM
Deputy Reinf. Concrete 9/22/2022 Conditional Approval ANDREW DORSO
Drywall Nailing 9/28/2022 Approved DANIEL VARNUM
T-Bar Ceiling 10/17/2022 Partial Inspection ANDREW DORSO
SGSOV-Seismic Gas S/O Valve 10/27/2022 SGSOV Not Ready JOHN KITCKO
Final 11/1/2022 Partial Inspection CAMERON CHABAN
Green Building Final 11/1/2022 Approved CAMERON CHABAN
SGSOV-Seismic Gas S/O Valve 11/1/2022 SGSOV No Gas CAMERON CHABAN
Smoke Detectors 11/1/2022 Approved CAMERON CHABAN
Final 11/5/2022 OK for TCO RICKEY JACKSON
Posting Pre-Inspection 11/5/2022 Approved RICKEY JACKSON
Special/Order Compliance 11/5/2022 Conditional Approval RICKEY JACKSON
Final 11/30/2022 Corrections Issued ANDREW DORSO
Final 1/10/2023 OK to Issue CofO BRIAN KELLY