8500 N BALBOA BLVD 91325
Certificate Information: 8500 N BALBOA BLVD 91325
- Application / Permit
- 21016-10000-09100
- Plan Check / Job No.
- B21LA06684
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (12) Manufacturing
- Work Description
- CHANGE OF USE FROM EXISTING MANUFACTURING TO OFFICE ON EXISTING 1ST FLOOR 148' X 245' & 62' X 91' ( 23050 SF) AND TENANT IMPROVEMENT FOR OFFICE ON EXISTING 1ST FLOOR 334' X 100' & EXISTING 2ND FLOOR 358' X 84' (48690 SF), NO STRUCTURAL CHANGES
- Permit Issued
- Issued on 8/23/2021
- Issuing Office
- Current Status
- Issued on 8/23/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/29/2021 | STARR CHEN |
| Corrections Issued | 5/1/2021 | STARR CHEN |
| Quality Review Completed | 5/20/2021 | KEN GILL |
| Disabled Access Plans Picked Up | 6/2/2021 | APPLICANT |
| Green Plans Picked Up | 6/3/2021 | APPLICANT |
| Applicant returned to address corrections | 6/10/2021 | STARR CHEN |
| Applicant returned to address corrections | 6/29/2021 | STARR CHEN |
| Plan Check Approved | 7/30/2021 | STARR CHEN |
| Issued | 8/23/2021 | APPLICANT |
| TCO Issued (Expire Date: 01-25-2023) | 7/29/2022 | JEFFREY DURAN |
| TCO Issued (Expire Date: 10-18-2023) | 4/21/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| ZA Case | Cleared | 5/20/2021 | LOUIS ORTEGA |
| ZA Case | Cleared | 5/20/2021 | LOUIS ORTEGA |
| Green Code | Cleared | 6/3/2021 | AARON COSTA |
| DAS Clearance | Cleared | 7/14/2021 | ELIZABETH TOMS |
Contact Information
| Architect | , ; Lic. No.: C22710 | , |
| Contractor | Clune Construction Company L P; Lic. No.: 732107-B | 725 SOUTH FIGUEROA STREET STE 300 LOS ANGELES, CA 90017 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Drywall Nailing | 10/25/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 10/25/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 10/27/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 10/27/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 10/28/2021 | Not Ready for Inspection | JEFFREY FULTON |
| Insulation | 10/28/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 11/3/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 11/3/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 11/16/2021 | Partial Approval | DANIEL VARNUM |
| Light Gage Steel Frame | 11/16/2021 | Approved | DANIEL VARNUM |
| Insulation | 11/18/2021 | Partial Inspection | JEFFREY FULTON |
| Insulation | 11/19/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 12/2/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 12/2/2021 | Partial Inspection | JEFFREY FULTON |
| Pre-Inspection | 12/8/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 12/13/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 12/16/2021 | Partial Inspection | JEFFREY FULTON |
| Insulation | 12/21/2021 | Partial Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 12/21/2021 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 12/30/2021 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 1/4/2022 | Conditional Approval | CAMERON CHABAN |
| Drywall Nailing | 1/7/2022 | Approved | JEFFREY FULTON |
| Footing/Foundation/Slab | 1/12/2022 | Partial Inspection | JEFFREY FULTON |
| Reinforced Concrete Frame | 1/12/2022 | Partial Inspection | JEFFREY FULTON |
| Deputy Reinf. Concrete | 1/13/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Reinf. Concrete | 1/14/2022 | Conditional Approval | JEFFREY FULTON |
| Drywall Nailing | 1/21/2022 | Partial Inspection | JEFFREY FULTON |
| Deputy Drilled-In Anchors | 1/27/2022 | Conditional Approval | JEFFREY FULTON |
| Deputy Reinf. Concrete | 1/27/2022 | Conditional Approval | JEFFREY FULTON |
| Smoke Detectors | 2/8/2022 | No Access for Inspection | JEFFREY FULTON |
| Light Gage Steel Frame | 2/11/2022 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 2/16/2022 | Partial Inspection | JEFFREY FULTON |
| Pre-Inspection | 2/23/2022 | Partial Inspection | JEFFREY FULTON |
| Green Building Rough | 3/3/2022 | Approved | JEFFREY FULTON |
| Wood Frame | 3/3/2022 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 3/24/2022 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 4/4/2022 | Approved | JEFFREY FULTON |
| Deputy Other (see comments) | 4/6/2022 | Conditional Approval | JEFFREY FULTON |
| Pre-Inspection | 4/7/2022 | Partial Inspection | JEFFREY FULTON |
| Drywall Nailing | 4/27/2022 | Partial Inspection | JEFFREY FULTON |
| T-Bar Ceiling | 4/27/2022 | Partial Inspection | JEFFREY FULTON |
| Wood Frame | 6/14/2022 | Partial Inspection | JEFFREY FULTON |
| Final | 7/15/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Green Building Final | 7/15/2022 | Approved | JEFFREY FULTON |
| SGSOV-Seismic Gas S/O Valve | 7/15/2022 | SGSOV No Gas | JEFFREY FULTON |
| Smoke Detectors | 7/15/2022 | Approved | JEFFREY FULTON |
| Wood Frame | 7/15/2022 | Approved | JEFFREY FULTON |
| Final | 7/20/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 8/3/2022 | Corrections Issued | JEFFREY FULTON |
| Deputy Reinf. Concrete | 8/26/2022 | Conditional Approval | JEFFREY FULTON |
| Insulation | 11/7/2022 | Partial Approval | KENNETH ROBERTS |
| Drywall Nailing | 11/10/2022 | Partial Inspection | JEFFREY FULTON |
| Pre-Inspection | 11/16/2022 | Partial Inspection | DEANDRE HOFFMAN |
| Special/Order Compliance | 11/16/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Final | 11/29/2022 | Partial Inspection | JEFFREY FULTON |
| Final | 4/20/2023 | Partial Inspection | DEANDRE HOFFMAN |
| Special/Order Compliance | 9/19/2023 | No Access for Inspection | DEANDRE HOFFMAN |
| Special/Order Compliance | 8/1/2024 | Corrections Issued | DEANDRE HOFFMAN |
| Final | 10/17/2025 | Partial Inspection | DEANDRE HOFFMAN |