539 N BERENDO ST 90004

Certificate Information: 539 N BERENDO ST 90004

Application / Permit
21016-10000-09064
Plan Check / Job No.
B21LA06659
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(22) Storage Building
Work Description
CONVERT EXIST. GARAGE/STORAGE BLDG. TO STORAGE AND ADDITION OF ATTACHED PATIO. TWO OPEN REQUIRED STANDARD SPACES TO BE PROVIDED. COMPLY WITH DEPT. ORDER DATED 11/16/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE.
Permit Issued
Issued on 7/6/2021
Issuing Office
Current Status
CofO Issued on 12/17/2021
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/12/2021 APPLICANT
Corrections Issued 4/17/2021 LAWRENCE QUIRANTE
Assigned to Plan Check Engineer 4/19/2021 LAWRENCE QUIRANTE
Building Plans Picked Up 4/20/2021 APPLICANT
Corrections Issued 5/19/2021 LAWRENCE QUIRANTE
Plan Check Approved 7/6/2021 TEODORO DIAZ RODRIGUEZ
Issued 7/6/2021 APPLICANT
CofO in Progress 10/13/2021 ALFREDO BALANDRA
CofO in Progress 12/15/2021 ALFREDO BALANDRA
CofO Issued 12/17/2021 DANIEL SANCHEZ
Permit Finaled 12/17/2021 DANIEL SANCHEZ

Permit Application Clearance Information

Specific Plan Cleared 5/20/2021 JASON HERNANDEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

RUBEN PEREZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
ROBERT NILES, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
MARK BEVELAQUA, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL SANCHEZ, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
COREY HUPP, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI
EMIL OPFFER, (213) 252-3053 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 9/1/2021 Partial Approval TIMOTHY MCCURDY
Footing/Foundation/Slab 9/1/2021 Partial Approval TIMOTHY MCCURDY
BUILDING-Rough-Frame 9/20/2021 Approved ALFREDO BALANDRA
Final 9/24/2021 Not Ready for Inspection ALFREDO BALANDRA
Footing/Foundation/Slab 9/24/2021 Corrections Issued ALFREDO BALANDRA
Interior/Exterior Lathing 9/24/2021 Approved ALFREDO BALANDRA
SGSOV-Seismic Gas S/O Valve 9/24/2021 SGSOV Approved ALFREDO BALANDRA
Smoke Detectors 9/24/2021 Corrections Issued ALFREDO BALANDRA
Wood Frame 9/24/2021 Approved ALFREDO BALANDRA
Final 10/4/2021 Not Ready for Inspection ALFREDO BALANDRA
Footing/Foundation/Slab 10/4/2021 Not Ready for Inspection ALFREDO BALANDRA
Smoke Detectors 10/4/2021 Approved ALFREDO BALANDRA
Final 10/6/2021 OK to Issue CofO ALFREDO BALANDRA
Footing/Foundation/Slab 10/6/2021 Approved ALFREDO BALANDRA