1130 N HUDSON AVE 90038

Certificate Information: 1130 N HUDSON AVE 90038

Application / Permit
21016-10000-09014
Plan Check / Job No.
B21LA06645
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMODEL TO SINGLE FAMILY DWELLING. REPLACE WINDOW AND DOORS. NEW INTERIOR BATHROOM. REMODEL TO KITCHEN TO REMOVE NON LOAD BEARING WALLS. REPLACE INTERIOR LOAD BEARING WALL AT LIVING ROOM. REPLACE EXTERIOR FINISHES AND REROOF.
Permit Issued
Issued on 6/7/2021
Issuing Office
Current Status
Permit Finaled on 11/19/2021

Permit Application Status History

Submitted 4/10/2021 APPLICANT
Assigned to Plan Check Engineer 4/15/2021 RICARDO RAMIREZ
Corrections Issued 4/16/2021 RICARDO RAMIREZ
Applicant returned to address corrections 5/12/2021 LAWRENCE QUIRANTE
Plan Check Approved 5/24/2021 RICARDO RAMIREZ
Issued 6/7/2021 APPLICANT
Building Plans Picked Up 6/8/2021 APPLICANT
Permit Finaled 11/18/2021 BRIAN SULLIVAN

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Kerr,, Gary Arthur; Lic. No.: C19693 272 BITTERN DRIVE      JOHNSTOWN, CO 80534
Contractor B & T Construction Llc; Lic. No.: 479804-B 21659 WO-HE-LO TRAIL      CHATSWORTH, CA 91311
Engineer Prentice,, Ronald Clifford; Lic. No.: C50406 16146 FALCON CREST DR      SAN DIEGO, CA 92127

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Wood Construction 6/10/2021 Conditional Approval BRIAN SULLIVAN
Footing/Foundation/Slab 6/15/2021 Approved BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 7/22/2021 Approved BRIAN SULLIVAN
BUILDING-Rough-Frame 8/11/2021 Approved BRIAN SULLIVAN
ELECTRICAL-Rough 8/11/2021 Approved BRIAN SULLIVAN
HVAC-Rough 8/11/2021 Approved BRIAN SULLIVAN
PLUMBING-Rough 8/11/2021 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 8/18/2021 Approved RAUL BARAJAS
Insulation 8/24/2021 Approved RAUL BARAJAS
Drywall Nailing 8/26/2021 Approved BRIAN SULLIVAN
Final 11/1/2021 Corrections Issued RAUL BARAJAS
SGSOV-Seismic Gas S/O Valve 11/1/2021 SGSOV Approved RAUL BARAJAS
Smoke Detectors 11/1/2021 Approved RAUL BARAJAS
Final 11/3/2021 Not Ready for Inspection BRIAN SULLIVAN
Final 11/18/2021 Permit Finaled BRIAN SULLIVAN