1217 S OGDEN DR UNIT 9 90019

Certificate Information: 1217 S OGDEN DR UNIT 9 90019

Application / Permit
21016-10000-09004
Plan Check / Job No.
B21LA06635
Group
Building
Type
Bldg-Addition
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CONVERT PORTION OF EXISTING CRAWL SPACE TO ADU (543SF) IN EXISTING 8 UNIT APARTMENT PER 65852.2(E)(1)(C), SEE COMMENTS
Permit Issued
Issued on 12/17/2021
Issuing Office
Current Status
CofO Issued on 7/2/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 STARR CHEN
Corrections Issued 4/24/2021 STARR CHEN
Quality Review Completed 4/28/2021 JASON HEALEY
Disabled Access Plans Picked Up 9/20/2021 APPLICANT
Applicant returned to address corrections 10/7/2021 STARR CHEN
Plan Check Approved 11/19/2021 STARR CHEN
Building Plans Picked Up 11/29/2021 APPLICANT
Issued 12/17/2021 APPLICANT
Green Plans Picked Up 1/30/2023 APPLICANT
CofO in Progress 7/2/2024 MARTIN TAVITIAN
CofO Issued 7/2/2024 ERNESTO CORRAL
Permit Finaled 7/2/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 4/30/2021 JEANIE LAM
Roof/Waste drainage to street Cleared 4/30/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 5/4/2021 JEANIE LAM
Sewer availability Cleared 5/4/2021 JEANIE LAM
Hydrant and Access approval Cleared 6/4/2021 JOHN CONNEALLY
Fire Marshal Fire Life Safety Cleared 9/9/2021 VIDAL GARCIA
DAS Clearance Cleared 9/16/2021 STARR CHEN

Contact Information

Architect Feld,, Dovid Yitzchak; Lic. No.: C37588 921 S HOLT AVENUE      LOS ANGELES, CA 90035
Contractor Dh Remodel Services; Lic. No.: 1030925-B 5850 W 3RD STREET #160      LOS ANGELES, CA 90036
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

IAN BLINN, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI
CHRISTOPHER BLACKWOOD, (213) 482-7361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/27/2022 Approved KATY RAMIREZ
Pre-Inspection 10/12/2022 No Access for Inspection KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 11/22/2022 Not Ready for Inspection KATY RAMIREZ
Special/Order Compliance 11/29/2022 Corrections Issued KATY RAMIREZ
Excavation/Setback/Form/Re-Bar 12/21/2022 Partial Inspection JEROME BLACKWOOD
Green Building Rough 2/28/2023 No Access for Inspection MARTIN TAVITIAN
Smoke Detectors 2/28/2023 No Access for Inspection MARTIN TAVITIAN
Final 4/19/2024 OK to Issue CofO MARTIN TAVITIAN
Footing/Foundation/Slab 4/19/2024 Approved MARTIN TAVITIAN
Green Building Final 4/19/2024 Approved MARTIN TAVITIAN
Green Building Rough 4/19/2024 Approved MARTIN TAVITIAN
METHANE-Barrier 4/19/2024 Approved MARTIN TAVITIAN
METHANE-Final 4/19/2024 Approved MARTIN TAVITIAN
METHANE-Rough 4/19/2024 Approved MARTIN TAVITIAN
METHANE-Subgrade 4/19/2024 Approved MARTIN TAVITIAN
SGSOV-Seismic Gas S/O Valve 4/19/2024 SGSOV Approved MARTIN TAVITIAN
Smoke Detectors 4/19/2024 Approved MARTIN TAVITIAN
Wood Frame 4/19/2024 Approved MARTIN TAVITIAN
Pre-Inspection 7/1/2024 Partial Approval MARTIN TAVITIAN