6635-6637 N PETIT AVE 91406

Certificate Information: 6635-6637 N PETIT AVE 91406

Application / Permit
21016-10000-08978
Plan Check / Job No.
B21LA06610
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan ADU addition. CONVERTING THE CARPORT AND PART OF SFD TO AN ADU (560 SQ.FT) - ADDITION AND REMODELING OF THE BATHROOM OF SFD ( 89 SQ.FT)
Permit Issued
Issued on 7/12/2021
Issuing Office
Current Status
CofO Issued on 2/17/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/14/2021 APPLICANT
Assigned to Plan Check Engineer 5/20/2021 ARSALAN SHABESTARI
Corrections Issued 5/29/2021 ARSALAN SHABESTARI
Quality Review Completed 6/4/2021 MICHAEL PEREZ
Plan Check Approved 6/26/2021 ARSALAN SHABESTARI
Plan Check Approved 6/27/2021 ARSALAN SHABESTARI
No Progress 6/27/2021 ARSALAN SHABESTARI
Plan Check Approved 6/27/2021 ARSALAN SHABESTARI
No Progress 6/27/2021 ARSALAN SHABESTARI
Plan Check Approved 6/27/2021 ARSALAN SHABESTARI
Issued 7/12/2021 APPLICANT
CofO in Progress 11/23/2022 RAUL OLAGI
Permit Finaled 2/17/2023 MICHAEL SMITH
CofO Issued 2/17/2023 MICHAEL SMITH
Permit Finaled 2/17/2023 MICHAEL SMITH

Permit Application Clearance Information

Address approval Cleared 6/8/2021 ADRIAN CASTRO
Eng Process Fee Ord 176,300 Cleared 6/8/2021 ADRIAN CASTRO
Roof/Waste drainage to street Cleared 6/8/2021 ADRIAN CASTRO
Sewer availability Cleared 6/8/2021 ADRIAN CASTRO
Watercourse Cleared 6/8/2021 ADRIAN CASTRO
ZI Cleared 6/9/2021 ANACANY HURTADO

Contact Information

Contractor B G Construction; Lic. No.: 469888-B 7317 WISH AVENUE      VAN NUYS, CA 91406

Inspector Information

MICHAEL CORTEZ, (818) 374-1176 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 10/29/2021 Partial Approval RAUL OLAGI
Deputy Drilled-In Anchors 11/15/2021 Conditional Approval RAUL OLAGI
Footing/Foundation/Slab 11/19/2021 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 1/13/2022 Conditional Approval RAUL OLAGI
Deputy Drilled-In Anchors 2/8/2022 Conditional Approval ALAN MORELOS
ELECTRICAL-Rough 4/6/2022 Approved RAUL OLAGI
Floor/Roof Diaphrgm/Shear Wall 4/6/2022 Approved RAUL OLAGI
PLUMBING-Rough 4/6/2022 Approved RAUL OLAGI
BUILDING-Rough-Frame 4/21/2022 Approved ALAN MORELOS
Green Building Rough 4/21/2022 Approved ALAN MORELOS
HVAC-Rough 4/21/2022 Approved ALAN MORELOS
Insulation 4/21/2022 Approved ALAN MORELOS
Interior/Exterior Lathing 4/21/2022 Partial Approval ALAN MORELOS
Drywall Nailing 4/27/2022 Approved DEANDRE HOFFMAN
Interior/Exterior Lathing 5/25/2022 Approved RAUL OLAGI
Final 11/15/2022 Corrections Issued RAUL OLAGI
Green Building Final 11/15/2022 Approved RAUL OLAGI
SGSOV-Seismic Gas S/O Valve 11/15/2022 SGSOV Approved RAUL OLAGI
Smoke Detectors 11/15/2022 Approved RAUL OLAGI
Final 11/23/2022 OK to Issue CofO RAUL OLAGI