21100 W ERWIN ST 91367
Certificate Information: 21100 W ERWIN ST 91367
- Application / Permit
- 21016-10000-08959
- Plan Check / Job No.
- B21LA06592
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (13) Medical Laboratory
- Work Description
- CHANGE OF USE & TENANT IMPROVEMENT 2-STORY OFFICE TO MEDICAL OFFICE/ RESEARCH WITH ACCESSORY VIVARIUM 1,200 SF , CONVERT EXISITNG INDOOR GARAGE TO MECHANICAL EQUIPMENT AREA . INTERIOR IMPROVEMENTS, RE-ROOF (E) ROOF & (N) ELEVATOR & RE-STRIPE PARKING. 1 OF 2
- Permit Issued
- Issued on 4/6/2022
- Issuing Office
- Current Status
- CofO Issued on 2/28/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/22/2021 | APPLICANT |
| Green Plans Picked Up | 5/24/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 5/26/2021 | ARMEN JIVALAGIAN |
| Corrections Issued | 6/1/2021 | ARMEN JIVALAGIAN |
| Quality Review Completed | 6/2/2021 | PETER KIM |
| Applicant returned to address corrections | 6/22/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 7/1/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 7/30/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 8/6/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 8/23/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 8/26/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/6/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 10/19/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 11/1/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 11/16/2021 | ARMEN JIVALAGIAN |
| Applicant returned to address corrections | 11/30/2021 | ARMEN JIVALAGIAN |
| Plan Check Approved | 3/30/2022 | ARMEN JIVALAGIAN |
| Issued | 4/6/2022 | APPLICANT |
| Building Plans Picked Up | 4/11/2022 | APPLICANT |
| CofO in Progress | 2/15/2023 | DANIEL VARNUM |
| Permit Finaled | 2/28/2023 | JEFFREY DURAN |
| CofO Issued | 2/28/2023 | JEFFREY DURAN |
| Permit Finaled | 2/28/2023 | JEFFREY DURAN |
Permit Application Clearance Information
| CPC | Cleared | 6/18/2021 | ANACANY HURTADO |
| Green Code | Cleared | 7/12/2021 | AARON COSTA |
| Eng Process Fee Ord 176,300 | Cleared | 8/14/2021 | JOHN LIN |
| Sewer availability | Cleared | 8/14/2021 | JOHN LIN |
| DAS Clearance | Cleared | 9/2/2021 | SHINE LIN |
| Prkng lot landscape/Water mgmt | Cleared | 9/10/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 9/14/2021 | WILLIAM JOHNS |
| Specific Plan | Cleared | 10/14/2021 | ANACANY HURTADO |
| Miscellaneous | Cleared | 1/31/2022 | ANACANY HURTADO |
| Fire Marshal Fire Life Safety | Cleared | 3/9/2022 | WILLIAM JOHNS |
| Internal circulation | Cleared | 3/18/2022 | DURRE SHAMSI |
| Specific Plan | Cleared | 3/18/2022 | DURRE SHAMSI |
Contact Information
| Architect | Kelsey,, Scott Patterson; Lic. No.: C15170 | 816 SOUTH DUNSMUIR AVENUE LOS ANGELES, CA 90036 |
| Contractor | Matt Construction Corporation; Lic. No.: 631020-B | 9814 NORWALK BLVD #100 SANTA FE SPRINGS, CA 90670 |
| Engineer | Hershberg,, Mark Aaron; Lic. No.: S5078 | 700 S FLOWER ST STE 2100 LOS ANGELES, CA 90017 |
Inspector Information
| JULIAN CAPUCETTI, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| STEVEN LEVITT, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| JACOB MYERS, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICARDO ROBLES, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| KENNETH ROBERTS, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUANELDA JOHNSON, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALAN NOVAK, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN YAKUBYAN, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| VAHE KELEDJIAN, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| JONATHAN QUACH, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| GRANT WOODS, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| JASON BORUTA, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
| KATY RAMIREZ, (213) 482-7097 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/15/2022 | Partial Inspection | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 4/18/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/18/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 4/21/2022 | Conditional Approval | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 4/21/2022 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | DANIEL VARNUM |
| Deputy Steel/Welding | 4/22/2022 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 4/26/2022 | Conditional Approval | KENNETH ROBERTS |
| Deputy Steel/Welding | 4/27/2022 | Conditional Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 4/27/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Footing/Foundation/Slab | 4/27/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Reinforced Concrete Frame | 4/27/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 4/28/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 4/28/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 4/28/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 4/29/2022 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 5/2/2022 | Partial Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 5/2/2022 | Partial Approval | ROBERT DAVIS |
| Wood Frame | 5/2/2022 | Partial Approval | ROBERT DAVIS |
| Deputy Reinf. Concrete | 5/3/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 5/3/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Wood Construction | 5/3/2022 | No Access for Inspection | DANIEL VARNUM |
| Deputy Steel/Welding | 5/4/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Wood Construction | 5/4/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 5/5/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 5/6/2022 | Conditional Approval | JEFFREY DURAN |
| Light Gage Steel Frame | 5/9/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Wood Frame | 5/9/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 5/11/2022 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 5/11/2022 | Partial Approval | DANIEL VARNUM |
| Reinforced Concrete Frame | 5/11/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 5/12/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 5/16/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 5/17/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 5/18/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Steel/Welding | 5/19/2022 | Conditional Approval | CAMERON CHABAN |
| Deputy Steel/Welding | 5/20/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 5/23/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 5/23/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 5/25/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Wood Construction | 5/25/2022 | Conditional Approval | JEFFREY DURAN |
| Wood Frame | 5/25/2022 | Partial Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 5/27/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 5/31/2022 | Approved | KENNETH ROBERTS |
| Deputy Reinf. Concrete | 5/31/2022 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 6/6/2022 | Conditional Approval | KENNETH ROBERTS |
| Deputy Drilled-In Anchors | 6/7/2022 | Conditional Approval | JEFFREY FULTON |
| Footing/Foundation/Slab | 6/7/2022 | Partial Approval | DANIEL VARNUM |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Inspection | CAMERON CHABAN |
| Deputy Wood Construction | 6/13/2022 | Conditional Approval | CAMERON CHABAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/13/2022 | Partial Inspection | DANIEL VARNUM |
| Wood Frame | 6/13/2022 | Partial Inspection | DANIEL VARNUM |
| Deputy Steel/Welding | 6/14/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Steel/Welding | 6/15/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Drilled-In Anchors | 6/22/2022 | Conditional Approval | ROBERT DAVIS |
| Insulation | 6/22/2022 | Partial Inspection | ROBERT DAVIS |
| Light Gage Steel Frame | 6/22/2022 | Partial Approval | ROBERT DAVIS |
| Deputy Drilled-In Anchors | 6/23/2022 | Conditional Approval | JEFFREY DURAN |
| Footing/Foundation/Slab | 6/27/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Reinf. Concrete | 6/28/2022 | Conditional Approval | JEFFREY DURAN |
| Deputy Wood Construction | 6/30/2022 | Conditional Approval | JEFFREY FULTON |
| Insulation | 6/30/2022 | Not Ready for Inspection | JEFFREY FULTON |
| Wood Frame | 6/30/2022 | Partial Inspection | JEFFREY FULTON |
| Insulation | 7/1/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 7/1/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 7/6/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 7/6/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 7/12/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Drywall Nailing | 7/18/2022 | Partial Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 7/28/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 8/3/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 8/3/2022 | Partial Approval | DANIEL VARNUM |
| Drywall Nailing | 8/15/2022 | Partial Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 8/15/2022 | Partial Approval | DANIEL VARNUM |
| Deputy Steel/Welding | 8/16/2022 | Conditional Approval | JEFFREY DURAN |
| Interior/Exterior Lathing | 8/25/2022 | Partial Inspection | DANIEL VARNUM |
| Light Gage Steel Frame | 8/25/2022 | Approved | DANIEL VARNUM |
| Pre-Inspection | 8/25/2022 | No Access for Inspection | DANIEL VARNUM |
| Deputy Steel/Welding | 8/29/2022 | Conditional Approval | JEFFREY DURAN |
| Drywall Nailing | 9/6/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Interior/Exterior Lathing | 9/6/2022 | Partial Approval | DANIEL VARNUM |
| T-Bar Ceiling | 9/20/2022 | Approved | DANIEL VARNUM |
| Deputy Steel/Welding | 9/30/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 10/19/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 10/21/2022 | Conditional Approval | DANIEL VARNUM |
| Footing/Foundation/Slab | 10/21/2022 | Approved | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 11/2/2022 | Conditional Approval | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 11/3/2022 | Conditional Approval | ANDREW DORSO |
| Deputy Reinf. Concrete | 11/14/2022 | Conditional Approval | DANIEL VARNUM |
| Final | 11/22/2022 | Partial Inspection | BRIAN KELLY |
| Green Building Final | 11/22/2022 | Partial Inspection | BRIAN KELLY |
| Green Building Rough | 11/22/2022 | Partial Inspection | BRIAN KELLY |
| Reinforced Masonry Frame | 11/22/2022 | Partial Inspection | BRIAN KELLY |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Not Ready | BRIAN KELLY |
| Smoke Detectors | 11/22/2022 | Partial Inspection | BRIAN KELLY |
| Final | 11/28/2022 | Partial Inspection | DANIEL VARNUM |
| Green Building Final | 11/28/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Rough | 11/28/2022 | Approved | DANIEL VARNUM |
| Reinforced Masonry Frame | 11/28/2022 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 11/28/2022 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 11/28/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Deputy Drilled-In Anchors | 12/12/2022 | Conditional Approval | BRIAN KELLY |
| Deputy Drilled-In Anchors | 12/13/2022 | Conditional Approval | JEFFREY DURAN |
| Final | 12/13/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Green Building Final | 12/13/2022 | Not Ready for Inspection | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 12/13/2022 | SGSOV Not Ready | DANIEL VARNUM |
| Smoke Detectors | 12/13/2022 | Not Ready for Inspection | DANIEL VARNUM |
| Pre-Inspection | 1/9/2023 | Partial Approval | DANIEL VARNUM |
| Final | 2/10/2023 | Partial Approval | DANIEL VARNUM |
| Green Building Final | 2/10/2023 | Approved | DANIEL VARNUM |
| SGSOV-Seismic Gas S/O Valve | 2/10/2023 | SGSOV No Gas | DANIEL VARNUM |
| Smoke Detectors | 2/10/2023 | Approved | DANIEL VARNUM |
| Final | 2/15/2023 | OK to Issue CofO | DANIEL VARNUM |