21100 W ERWIN ST 91367

Certificate Information: 21100 W ERWIN ST 91367

Application / Permit
21016-10000-08959
Plan Check / Job No.
B21LA06592
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Commercial
Primary Use
(13) Medical Laboratory
Work Description
CHANGE OF USE & TENANT IMPROVEMENT 2-STORY OFFICE TO MEDICAL OFFICE/ RESEARCH WITH ACCESSORY VIVARIUM 1,200 SF , CONVERT EXISITNG INDOOR GARAGE TO MECHANICAL EQUIPMENT AREA . INTERIOR IMPROVEMENTS, RE-ROOF (E) ROOF & (N) ELEVATOR & RE-STRIPE PARKING. 1 OF 2
Permit Issued
Issued on 4/6/2022
Issuing Office
Current Status
CofO Issued on 2/28/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 4/22/2021 APPLICANT
Green Plans Picked Up 5/24/2021 APPLICANT
Assigned to Plan Check Engineer 5/26/2021 ARMEN JIVALAGIAN
Corrections Issued 6/1/2021 ARMEN JIVALAGIAN
Quality Review Completed 6/2/2021 PETER KIM
Applicant returned to address corrections 6/22/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/1/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 7/30/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/6/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/23/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 8/26/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/6/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 10/19/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/1/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/16/2021 ARMEN JIVALAGIAN
Applicant returned to address corrections 11/30/2021 ARMEN JIVALAGIAN
Plan Check Approved 3/30/2022 ARMEN JIVALAGIAN
Issued 4/6/2022 APPLICANT
Building Plans Picked Up 4/11/2022 APPLICANT
CofO in Progress 2/15/2023 DANIEL VARNUM
Permit Finaled 2/28/2023 JEFFREY DURAN
CofO Issued 2/28/2023 JEFFREY DURAN
Permit Finaled 2/28/2023 JEFFREY DURAN

Permit Application Clearance Information

CPC Cleared 6/18/2021 ANACANY HURTADO
Green Code Cleared 7/12/2021 AARON COSTA
Eng Process Fee Ord 176,300 Cleared 8/14/2021 JOHN LIN
Sewer availability Cleared 8/14/2021 JOHN LIN
DAS Clearance Cleared 9/2/2021 SHINE LIN
Prkng lot landscape/Water mgmt Cleared 9/10/2021 ANACANY HURTADO
Miscellaneous Cleared 9/14/2021 WILLIAM JOHNS
Specific Plan Cleared 10/14/2021 ANACANY HURTADO
Miscellaneous Cleared 1/31/2022 ANACANY HURTADO
Fire Marshal Fire Life Safety Cleared 3/9/2022 WILLIAM JOHNS
Internal circulation Cleared 3/18/2022 DURRE SHAMSI
Specific Plan Cleared 3/18/2022 DURRE SHAMSI

Contact Information

Architect Kelsey,, Scott Patterson; Lic. No.: C15170 816 SOUTH DUNSMUIR AVENUE      LOS ANGELES, CA 90036
Contractor Matt Construction Corporation; Lic. No.: 631020-B 9814 NORWALK BLVD #100      SANTA FE SPRINGS, CA 90670
Engineer Hershberg,, Mark Aaron; Lic. No.: S5078 700 S FLOWER ST STE 2100      LOS ANGELES, CA 90017

Inspector Information

JULIAN CAPUCETTI, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
STEVEN LEVITT, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
JACOB MYERS, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
RICARDO ROBLES, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
KENNETH ROBERTS, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
JUANELDA JOHNSON, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
ALAN NOVAK, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
JOHN YAKUBYAN, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
VAHE KELEDJIAN, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
JONATHAN QUACH, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
GRANT WOODS, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
JASON BORUTA, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI
KATY RAMIREZ, (213) 482-7097 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2022 Partial Inspection DANIEL VARNUM
Deputy Drilled-In Anchors 4/18/2022 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/18/2022 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 4/21/2022 Conditional Approval KENNETH ROBERTS
Deputy Reinf. Concrete 4/21/2022 Conditional Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Approved DANIEL VARNUM
Deputy Steel/Welding 4/22/2022 Conditional Approval KENNETH ROBERTS
Deputy Steel/Welding 4/26/2022 Conditional Approval KENNETH ROBERTS
Deputy Steel/Welding 4/27/2022 Conditional Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Not Ready for Inspection DANIEL VARNUM
Footing/Foundation/Slab 4/27/2022 Not Ready for Inspection DANIEL VARNUM
Reinforced Concrete Frame 4/27/2022 Partial Approval DANIEL VARNUM
Deputy Drilled-In Anchors 4/28/2022 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 4/28/2022 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 4/28/2022 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 4/29/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 5/2/2022 Partial Inspection ROBERT DAVIS
Light Gage Steel Frame 5/2/2022 Partial Approval ROBERT DAVIS
Wood Frame 5/2/2022 Partial Approval ROBERT DAVIS
Deputy Reinf. Concrete 5/3/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 5/3/2022 Conditional Approval CAMERON CHABAN
Deputy Wood Construction 5/3/2022 No Access for Inspection DANIEL VARNUM
Deputy Steel/Welding 5/4/2022 Conditional Approval DANIEL VARNUM
Deputy Wood Construction 5/4/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 5/5/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 5/6/2022 Conditional Approval JEFFREY DURAN
Light Gage Steel Frame 5/9/2022 Not Ready for Inspection DANIEL VARNUM
Wood Frame 5/9/2022 Partial Approval DANIEL VARNUM
Deputy Drilled-In Anchors 5/11/2022 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 5/11/2022 Partial Approval DANIEL VARNUM
Reinforced Concrete Frame 5/11/2022 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 5/12/2022 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 5/16/2022 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 5/17/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 5/18/2022 Conditional Approval ANDREW DORSO
Deputy Steel/Welding 5/19/2022 Conditional Approval CAMERON CHABAN
Deputy Steel/Welding 5/20/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 5/23/2022 Conditional Approval DANIEL VARNUM
Deputy Steel/Welding 5/23/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 5/25/2022 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 5/25/2022 Conditional Approval JEFFREY DURAN
Wood Frame 5/25/2022 Partial Inspection ANDREW DORSO
Footing/Foundation/Slab 5/27/2022 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 5/31/2022 Approved KENNETH ROBERTS
Deputy Reinf. Concrete 5/31/2022 Conditional Approval KENNETH ROBERTS
Deputy Drilled-In Anchors 6/6/2022 Conditional Approval KENNETH ROBERTS
Deputy Drilled-In Anchors 6/7/2022 Conditional Approval JEFFREY FULTON
Footing/Foundation/Slab 6/7/2022 Partial Approval DANIEL VARNUM
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Inspection CAMERON CHABAN
Deputy Wood Construction 6/13/2022 Conditional Approval CAMERON CHABAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2022 Partial Inspection DANIEL VARNUM
Wood Frame 6/13/2022 Partial Inspection DANIEL VARNUM
Deputy Steel/Welding 6/14/2022 Conditional Approval JEFFREY DURAN
Deputy Steel/Welding 6/15/2022 Conditional Approval JEFFREY DURAN
Deputy Drilled-In Anchors 6/22/2022 Conditional Approval ROBERT DAVIS
Insulation 6/22/2022 Partial Inspection ROBERT DAVIS
Light Gage Steel Frame 6/22/2022 Partial Approval ROBERT DAVIS
Deputy Drilled-In Anchors 6/23/2022 Conditional Approval JEFFREY DURAN
Footing/Foundation/Slab 6/27/2022 Partial Approval DANIEL VARNUM
Deputy Reinf. Concrete 6/28/2022 Conditional Approval JEFFREY DURAN
Deputy Wood Construction 6/30/2022 Conditional Approval JEFFREY FULTON
Insulation 6/30/2022 Not Ready for Inspection JEFFREY FULTON
Wood Frame 6/30/2022 Partial Inspection JEFFREY FULTON
Insulation 7/1/2022 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 7/1/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 7/6/2022 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 7/6/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 7/12/2022 Not Ready for Inspection DANIEL VARNUM
Drywall Nailing 7/18/2022 Partial Inspection DANIEL VARNUM
Light Gage Steel Frame 7/28/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 8/3/2022 Not Ready for Inspection DANIEL VARNUM
Light Gage Steel Frame 8/3/2022 Partial Approval DANIEL VARNUM
Drywall Nailing 8/15/2022 Partial Inspection DANIEL VARNUM
Light Gage Steel Frame 8/15/2022 Partial Approval DANIEL VARNUM
Deputy Steel/Welding 8/16/2022 Conditional Approval JEFFREY DURAN
Interior/Exterior Lathing 8/25/2022 Partial Inspection DANIEL VARNUM
Light Gage Steel Frame 8/25/2022 Approved DANIEL VARNUM
Pre-Inspection 8/25/2022 No Access for Inspection DANIEL VARNUM
Deputy Steel/Welding 8/29/2022 Conditional Approval JEFFREY DURAN
Drywall Nailing 9/6/2022 Not Ready for Inspection DANIEL VARNUM
Interior/Exterior Lathing 9/6/2022 Partial Approval DANIEL VARNUM
T-Bar Ceiling 9/20/2022 Approved DANIEL VARNUM
Deputy Steel/Welding 9/30/2022 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 10/19/2022 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 10/21/2022 Conditional Approval DANIEL VARNUM
Footing/Foundation/Slab 10/21/2022 Approved DANIEL VARNUM
Deputy Drilled-In Anchors 11/2/2022 Conditional Approval DANIEL VARNUM
Deputy Drilled-In Anchors 11/3/2022 Conditional Approval ANDREW DORSO
Deputy Reinf. Concrete 11/14/2022 Conditional Approval DANIEL VARNUM
Final 11/22/2022 Partial Inspection BRIAN KELLY
Green Building Final 11/22/2022 Partial Inspection BRIAN KELLY
Green Building Rough 11/22/2022 Partial Inspection BRIAN KELLY
Reinforced Masonry Frame 11/22/2022 Partial Inspection BRIAN KELLY
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Not Ready BRIAN KELLY
Smoke Detectors 11/22/2022 Partial Inspection BRIAN KELLY
Final 11/28/2022 Partial Inspection DANIEL VARNUM
Green Building Final 11/28/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Rough 11/28/2022 Approved DANIEL VARNUM
Reinforced Masonry Frame 11/28/2022 Approved DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 11/28/2022 Not Ready for Inspection DANIEL VARNUM
Deputy Drilled-In Anchors 12/12/2022 Conditional Approval BRIAN KELLY
Deputy Drilled-In Anchors 12/13/2022 Conditional Approval JEFFREY DURAN
Final 12/13/2022 Not Ready for Inspection DANIEL VARNUM
Green Building Final 12/13/2022 Not Ready for Inspection DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 12/13/2022 SGSOV Not Ready DANIEL VARNUM
Smoke Detectors 12/13/2022 Not Ready for Inspection DANIEL VARNUM
Pre-Inspection 1/9/2023 Partial Approval DANIEL VARNUM
Final 2/10/2023 Partial Approval DANIEL VARNUM
Green Building Final 2/10/2023 Approved DANIEL VARNUM
SGSOV-Seismic Gas S/O Valve 2/10/2023 SGSOV No Gas DANIEL VARNUM
Smoke Detectors 2/10/2023 Approved DANIEL VARNUM
Final 2/15/2023 OK to Issue CofO DANIEL VARNUM