652 N HAYWORTH AVE 90048

Certificate Information: 652 N HAYWORTH AVE 90048

Application / Permit
21016-10000-08811
Plan Check / Job No.
B21LA06517
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
SOFT STORY RETROFIT AS PER LABC CH- 93. USING STEEL SPECIAL CANTILEVER COLUMN SYSTEM (SCCS)
Permit Issued
Issued on 9/29/2022
Issuing Office
Metro
Current Status
Issued on 9/29/2022

Permit Application Status History

Submitted 4/9/2021 APPLICANT
Assigned to Plan Check Engineer 4/29/2021 YOUNG KIM
Corrections Issued 5/12/2021 YOUNG KIM
Quality Review Completed 5/13/2021 HANS SANTIAGO
Building Plans Picked Up 5/20/2021 APPLICANT
Applicant returned to address corrections 8/24/2021 YOUNG KIM
Applicant returned to address corrections 8/26/2021 YOUNG KIM
Applicant returned to address corrections 12/7/2021 YOUNG KIM
Applicant returned to address corrections 12/21/2021 YOUNG KIM
Applicant returned to address corrections 2/24/2022 YOUNG KIM
Plan Check Approved 3/4/2022 YOUNG KIM
No Progress 6/13/2022 VARAND SARKISIAN
Plan Check Approved 6/13/2022 VARAND SARKISIAN
Issued 9/29/2022 APPLICANT

Permit Application Clearance Information

Construction near power lines Cleared 5/31/2022 WALTER RAMIREZ
Construction within easement Cleared 5/31/2022 WALTER RAMIREZ
Tenant Habitability Plan Cleared 9/26/2022 RICARDO BOHORQUEZ

Contact Information

Architect Salcedo,, Glen Charles; Lic. No.: C33143 P O BOX 14202      VAN NUYS, CA 91409
Contractor Bak Construction; Lic. No.: 1060027-B 4435 NOGALES DR      TARZANA, CA 91356
Engineer Mourad,, Daniel; Lic. No.: C83387 542 N FULLER AVE      LOS ANGELES, CA 90036

Inspector Information

DARRYL ARNOLD, (213) 482-0341 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/4/2022 Conditional Approval DARRYL ARNOLD
Deputy Steel/Welding 11/29/2022 Conditional Approval DARRYL ARNOLD
Deputy Drilled-In Anchors 12/6/2022 Conditional Approval DARRYL ARNOLD
Footing/Foundation/Slab 12/7/2022 Corrections Issued VAHE KELEDJIAN
Structural Steel Frame 12/7/2022 Not Ready for Inspection VAHE KELEDJIAN
Wood Frame 12/7/2022 Partial Approval VAHE KELEDJIAN
Footing/Foundation/Slab 12/15/2022 Partial Approval VAHE KELEDJIAN
Wood Frame 12/27/2022 Corrections Issued VAHE KELEDJIAN
Floor/Roof Diaphrgm/Shear Wall 12/30/2022 Partial Approval VAHE KELEDJIAN
Floor/Roof Diaphrgm/Shear Wall 1/6/2023 Corrections Issued BRUCE CAMPBELL
Deputy Wood Construction 1/9/2023 Partial Approval DARRYL ARNOLD
Deputy Steel/Welding 1/10/2023 Conditional Approval DARRYL ARNOLD
Excavation/Setback/Form/Re-Bar 1/12/2023 Partial Approval VAHE KELEDJIAN
Floor/Roof Diaphrgm/Shear Wall 1/12/2023 Partial Approval VAHE KELEDJIAN
Interior/Exterior Lathing 1/26/2023 Partial Approval BRUCE CAMPBELL
Interior/Exterior Lathing 1/30/2023 Partial Approval BRUCE CAMPBELL
Excavation/Setback/Form/Re-Bar 2/10/2023 Approved BRUCE CAMPBELL
Structural Steel Frame 2/10/2023 Approved BRUCE CAMPBELL
Wood Frame 2/10/2023 Approved BRUCE CAMPBELL
Floor/Roof Diaphrgm/Shear Wall 2/21/2023 Conditional Approval JAIME RIOS
Insulation 2/21/2023 Conditional Approval JAIME RIOS
Interior/Exterior Lathing 2/23/2023 Approved VAHE KELEDJIAN