4805 S CENTRAL AVE 1-4 90011

Certificate Information: 4805 S CENTRAL AVE 1-4 90011

Application / Permit
21016-10000-08804
Plan Check / Job No.
B21LA06512
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
CHANGE OF USE ON 2ND STORY OF (E) MEDICAL OFFICES TO (N) 4 APARTMENT UNITS
Permit Issued
Issued on 5/13/2022
Issuing Office
Metro
Current Status
Issued on 5/13/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 4/8/2021 APPLICANT
Assigned to Plan Check Engineer 4/22/2021 LAMAR DAVIS
Corrections Issued 5/3/2021 LAMAR DAVIS
Quality Review Completed 5/12/2021 WING SUEN
Building Plans Picked Up 6/2/2021 APPLICANT
Applicant returned to address corrections 1/5/2022 LAMAR DAVIS
Plan Check Approved 5/3/2022 LAMAR DAVIS
Issued 5/13/2022 APPLICANT
TCO Issued (Expire Date: 10-28-2026) 5/1/2026 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 12/10/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/13/2021 CHRISTOPHER ROCHA
Community Plan Implem. Overlay Cleared 12/14/2021 HELEN JADALI
Historic Resource Verification Cleared 12/16/2021 MAX LODER
Redevelopment Project Area Cleared 12/29/2021 DAVID URITA
Sewer availability Cleared 12/30/2021 CHRISTOPHER ROCHA
DAS Clearance Cleared 2/7/2022 LAMAR DAVIS

Contact Information

Contractor La Casa Building Contractors; Lic. No.: 537961-B 5425 S CENTRAL AVE      LOS ANGELES, CA 90011
Engineer Lee,, Sang Youck; Lic. No.: S3821 3531 BROOKHILL ST      GLENDALE, CA 91214

Inspector Information

PAUL BAZERKANIAN, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
LUIS CCAMACHO, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI
ALAN MORELOS, (213) 482-0353 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 6/13/2022 Conditional Approval ERNESTO CORRAL
Footing/Foundation/Slab 6/16/2022 Approved TIMOTHY BUXTON
Deputy Reinf. Concrete 6/17/2022 Conditional Approval TIMOTHY BUXTON
Wood Frame 6/29/2022 Partial Approval RUSSELL BONVOULOIR
Structural Steel Frame 7/7/2022 Conditional Approval DARRYL ARNOLD
Drywall Nailing 7/11/2022 Partial Approval RUSSELL BONVOULOIR
Wood Frame 10/31/2022 Partial Inspection RUSSELL BONVOULOIR
Deputy Wood Construction 11/22/2022 Conditional Approval RUSSELL BONVOULOIR
Insulation 12/20/2022 Approved ALAN MORELOS
Wood Frame 12/20/2022 Partial Inspection ALAN MORELOS
Interior/Exterior Lathing 12/27/2022 Partial Approval ALAN MORELOS
Drywall Nailing 1/12/2023 Conditional Approval DARRYL ARNOLD
Insulation 1/17/2023 Approved MARTIN TAVITIAN
Final 2/23/2026 Not Ready for Inspection ALFREDO LOPEZ
SGSOV-Seismic Gas S/O Valve 2/23/2026 SGSOV Not Ready ALFREDO LOPEZ
Smoke Detectors 2/23/2026 Not Ready for Inspection ALFREDO LOPEZ
Wood Frame 2/23/2026 Approved ALFREDO LOPEZ
Final 4/9/2026 Not Ready for Inspection JAMES POWERS
SGSOV-Seismic Gas S/O Valve 4/9/2026 SGSOV Approved JAMES POWERS
Smoke Detectors 4/9/2026 Approved JAMES POWERS
Final 4/22/2026 Approved PAUL BAZERKANIAN
Final 4/30/2026 OK for TCO JAMES POWERS