11980 W FOOTHILL BLVD 91342
Certificate Information: 11980 W FOOTHILL BLVD 91342
- Application / Permit
- 21016-10000-08797
- Plan Check / Job No.
- B21LA06506
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- Commercial
- Primary Use
- (17) Restaurant
- Work Description
- TI & CHANGE OF USE OF EXISTING RESTAURANT & RETAIL SPACES INTO A RESTAURANT WITH OUTDOOR EATING & DRIVE THROUGH. NEW ROOFTOP EQUIPMENT/STORE FRONTS & WINDOWS.
- Permit Issued
- Issued on 9/1/2021
- Issuing Office
- Current Status
- Issued on 9/1/2021
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/22/2021 | KESETE HAREGOT |
| Corrections Issued | 4/28/2021 | KESETE HAREGOT |
| Quality Review Completed | 4/30/2021 | FARUK SEZER |
| Building Plans Picked Up | 5/5/2021 | APPLICANT |
| Green Plans Picked Up | 6/9/2021 | APPLICANT |
| Plan Check Approved | 9/1/2021 | KESETE HAREGOT |
| Issued | 9/1/2021 | APPLICANT |
| TCO Issued (Expire Date: 11-02-2022) | 5/6/2022 | JEFFREY DURAN |
| TCO Issued (Expire Date: 05-06-2023) | 11/7/2022 | JEFFREY DURAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/11/2021 | GABRIEL ROBLES |
| Sewer availability | Cleared | 5/11/2021 | GABRIEL ROBLES |
| Green Code | Cleared | 6/8/2021 | AARON COSTA |
| Comm Cor/Mini-Mall | Cleared | 6/22/2021 | DANIEL CORONADO |
| Comm Cor/Mini-Mall | Cleared | 6/22/2021 | DANIEL CORONADO |
| Comm Cor/Mini-Mall | Cleared | 6/22/2021 | DANIEL CORONADO |
| Drive Through | Cleared | 6/24/2021 | DURRE SHAMSI |
| DAS Clearance | Cleared | 8/10/2021 | SHINE LIN |
| Food establishment approval | Cleared | 8/31/2021 | LACDHS APPROVED |
Contact Information
| Architect | Lingle,, Carl Lee; Lic. No.: C29985 | 9113 IL 73 NORTH WINSLOW, IL 61089 |
| Contractor | Construct & Maintain Corp; Lic. No.: 817124-B | 27075 CABOT RD STE #114 LAGUNA HILLS, CA 92653 |
Inspector Information
| ANDREW DORSO, (818) 374-7520 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 9/20/2021 | Partial Inspection | ANDREW DORSO |
| Insulation | 9/30/2021 | Corrections Issued | ANDREW DORSO |
| Structural Steel Frame | 9/30/2021 | Not Ready for Inspection | ANDREW DORSO |
| Footing/Foundation/Slab | 10/6/2021 | Partial Inspection | ANDREW DORSO |
| Insulation | 10/6/2021 | Approved | ANDREW DORSO |
| Light Gage Steel Frame | 10/12/2021 | Not Ready for Inspection | ANDREW DORSO |
| Drywall Nailing | 10/18/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 10/18/2021 | Partial Inspection | ANDREW DORSO |
| Light Gage Steel Frame | 10/19/2021 | Not Ready for Inspection | ANDREW DORSO |
| Excavation/Setback/Form/Re-Bar | 11/10/2021 | Not Ready for Inspection | KENNETH ROBERTS |
| Light Gage Steel Frame | 11/12/2021 | Approved | ANDREW DORSO |
| Drywall Nailing | 11/15/2021 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 12/13/2021 | Conditional Approval | DANIEL VARNUM |
| T-Bar Ceiling | 12/14/2021 | Not Ready for Inspection | ANDREW DORSO |
| Final | 3/29/2022 | Not Ready for Inspection | ANDREW DORSO |
| Green Building Rough | 3/29/2022 | Approved | ANDREW DORSO |
| T-Bar Ceiling | 4/13/2022 | Not Ready for Inspection | ANDREW DORSO |
| T-Bar Ceiling | 4/18/2022 | Not Ready for Inspection | DANIEL VARNUM |
| T-Bar Ceiling | 4/26/2022 | Approved | DANNY RODRIGUEZ |
| Final | 9/30/2022 | Partial Approval | ANDREW DORSO |
| Green Building Final | 9/30/2022 | Approved | ANDREW DORSO |
| SGSOV-Seismic Gas S/O Valve | 9/30/2022 | SGSOV Approved | ANDREW DORSO |
| Smoke Detectors | 9/30/2022 | Approved | ANDREW DORSO |
| Wood Frame | 9/30/2022 | Approved | ANDREW DORSO |
| Special/Order Compliance | 10/5/2022 | Partial Approval | ANDREW DORSO |
| Special/Order Compliance | 4/12/2023 | Not Ready for Inspection | JEFFREY DURAN |
| Special/Order Compliance | 4/24/2023 | Conditional Approval | ANDREW DORSO |