12141 W MARSHALL ST 90230
Certificate Information: 12141 W MARSHALL ST 90230
- Application / Permit
- 21016-10000-08781
- Plan Check / Job No.
- B21LA06498
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- Interior remodel to (E) SFD (1623 SF). Scope of work to include: Kitchen remodel by removing wall and adding (N) beam, (E) Bathroom #2 Remodel, Replace (E) water heater with (N) Tankless water heater, Adding (N) Central HVAC to attic, Replace (E) Doors and Windows, Interior paint and floor re-finish. All Structural Work per Engineered Design.
- Permit Issued
- Issued on 6/4/2021
- Issuing Office
- Current Status
- Permit Finaled on 12/3/2021
Permit Application Status History
| Submitted | 4/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/13/2021 | AARON COSTA |
| Corrections Issued | 4/13/2021 | AARON COSTA |
| Plan Check Approved | 4/30/2021 | RICARDO RAMIREZ |
| Issued | 6/4/2021 | APPLICANT |
| Building Plans Picked Up | 6/8/2021 | APPLICANT |
| Permit Finaled | 12/3/2021 | ENRIQUE MIRELES |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Misong Corporation; Lic. No.: 755122-B | 936 S ALVARADO STREET LOS ANGELES, CA 90006 |
| Engineer | Park,, Juntae; Lic. No.: C65104 | 3055 WILSHIRE BLVD 880 LOS ANGELES, CA 90010 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/21/2021 | Corrections Issued | CHRISTOPHER WILSON |
| Footing/Foundation/Slab | 7/1/2021 | Approved | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/13/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 7/13/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/13/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| HVAC-Rough | 7/13/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/13/2021 | Not Ready for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 7/15/2021 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/15/2021 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 7/15/2021 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/15/2021 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 8/9/2021 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Drywall Nailing | 8/12/2021 | Approved | ENRIQUE MIRELES |
| Final | 12/3/2021 | Permit Finaled | ENRIQUE MIRELES |
| SGSOV-Seismic Gas S/O Valve | 12/3/2021 | SGSOV Approved | ENRIQUE MIRELES |
| Smoke Detectors | 12/3/2021 | Approved | ENRIQUE MIRELES |