555-557 W 13TH ST 90731
Certificate Information: 555-557 W 13TH ST 90731
- Application / Permit
- 21016-10000-08744
- Plan Check / Job No.
- B21LA06489
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- EXISITING SFD (REAR) TO BE CONVERTED INTO SFD & ADU PER STATE LAW
- Permit Issued
- Issued on 4/6/2022
- Issuing Office
- Current Status
- CofO Issued on 6/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 4/12/2021 | FERNANDO FLORES |
| Corrections Issued | 4/12/2021 | FERNANDO FLORES |
| Plan Check Approved | 3/19/2022 | FERNANDO FLORES |
| Issued | 4/6/2022 | APPLICANT |
| Building Plans Picked Up | 4/12/2022 | APPLICANT |
| CofO in Progress | 6/18/2024 | JAMES CHAVEZ |
| Permit Finaled | 6/18/2024 | ANSON MAGLASANG |
| CofO Issued | 6/18/2024 | ANSON MAGLASANG |
| Permit Finaled | 6/18/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 4/20/2021 | CHINH DINH |
| Sewer availability | Cleared | 4/20/2021 | CHINH DINH |
| Historic Resource Verification | Cleared | 5/21/2021 | MICAELA TORRES-GIL |
| Redevelopment Project Area | Cleared | 6/8/2021 | DAVID URITA |
| ZA Case | Cleared | 6/14/2021 | RUBEN VASQUEZ |
| Eng Process Fee Ord 176,300 | Cleared | 7/20/2021 | CHINH DINH |
| Community Plan Implem. Overlay | Cleared | 8/11/2021 | JEANALEE OBERGFELL |
| Tenant Habitability Plan | Cleared | 8/11/2021 | JEFFREY BULL |
Contact Information
| Contractor | J A Enterprises Inc; Lic. No.: 981375-B | 4531 GUNDRY AVENUE LONG BEACH, CA 90807 |
| Engineer | Ramirez, Cid, Jose Carlos; Lic. No.: C91046 | 5164 N RATON CIR LONG BEACH, CA 90807 |
Inspector Information
| JOSEPH MCGARRY, (310) 732-4559 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/30/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Footing/Foundation/Slab | 7/14/2022 | Partial Approval | EUGENE CASSIDY |
| Footing/Foundation/Slab | 8/4/2022 | Approved | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 9/20/2022 | Corrections Issued | ANSON MAGLASANG |
| PLUMBING-Rough | 9/20/2022 | Corrections Issued | ANSON MAGLASANG |
| Wood Frame | 9/20/2022 | Corrections Issued | ANSON MAGLASANG |
| Deputy Drilled-In Anchors | 11/15/2022 | Conditional Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 11/15/2022 | No Access for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 11/15/2022 | No Access for Inspection | ANSON MAGLASANG |
| ELECTRICAL-Rough | 11/21/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| Floor/Roof Diaphrgm/Shear Wall | 11/21/2022 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 11/21/2022 | Approved | ALIZAH MAYAGOITIA |
| Deputy Wood Construction | 12/5/2022 | Conditional Approval | ANSON MAGLASANG |
| ELECTRICAL-Rough | 12/19/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| HVAC-Rough | 12/19/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 12/19/2022 | Corrections Issued | ANSON MAGLASANG |
| ELECTRICAL-Rough | 12/27/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| Insulation | 12/27/2022 | Not Ready for Inspection | ANSON MAGLASANG |
| PLUMBING-Rough | 12/27/2022 | Approved | ANSON MAGLASANG |
| ELECTRICAL-Rough | 1/23/2023 | Approved | JOHN KLARIN |
| Insulation | 1/23/2023 | Not Ready for Inspection | JOHN KLARIN |
| PLUMBING-Rough | 1/23/2023 | Approved | JOHN KLARIN |
| Wood Frame | 1/23/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 1/30/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 1/30/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 4/5/2024 | Approved | JAMES CHAVEZ |
| Final | 4/5/2024 | Corrections Issued | JAMES CHAVEZ |
| SGSOV-Seismic Gas S/O Valve | 4/5/2024 | SGSOV Not Ready | JAMES CHAVEZ |
| Smoke Detectors | 4/5/2024 | Not Ready for Inspection | JAMES CHAVEZ |
| ELECTRICAL-Final | 4/17/2024 | Partial Approval | EUGENE CASSIDY |
| Final | 4/17/2024 | Corrections Issued | EUGENE CASSIDY |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Approved | EUGENE CASSIDY |
| Smoke Detectors | 4/17/2024 | Approved | EUGENE CASSIDY |
| Final | 6/5/2024 | Corrections Issued | JAMES CHAVEZ |
| Final | 6/11/2024 | OK to Issue CofO | JAMES CHAVEZ |