504-504 1/2 E ALTAIR PL 90291

Certificate Information: 504-504 1/2 E ALTAIR PL 90291

Application / Permit
21016-10000-08726
Plan Check / Job No.
B21LA06473
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
CONVERT (E) STORAGE AREA (439 SF) OF DUPLEX INTO NEW ATTACHED ADU PER ORDINANCE
Permit Issued
Issued on 8/19/2022
Issuing Office
Metro
Current Status
CofO Issued on 4/16/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/27/2021 APPLICANT
Assigned to Plan Check Engineer 6/17/2021 CARLOS MONTES
Corrections Issued 6/22/2021 CARLOS MONTES
Quality Review Completed 6/30/2021 WING SUEN
Building Plans Picked Up 7/6/2021 APPLICANT
Plan Check Approved 8/10/2022 CARLOS MONTES
Issued 8/19/2022 APPLICANT
CofO in Progress 4/12/2024 HERBERT GIRON
Permit Finaled 4/16/2024 DANIEL ORRANTE
CofO Issued 4/16/2024 DANIEL ORRANTE
Permit Finaled 4/16/2024 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 7/19/2021 RAYMOND MUGAMBWA
Eng Process Fee Ord 176,300 Cleared 7/22/2021 RAYMOND MUGAMBWA
Highway dedication Cleared 8/11/2021 RAYMOND MUGAMBWA
Miscellaneous Cleared 8/11/2021 RAYMOND MUGAMBWA
Sewer availability Cleared 8/11/2021 RAYMOND MUGAMBWA
Miscellaneous Cleared 9/2/2021 RUBEN VASQUEZ
Miscellaneous Cleared 9/2/2021 RUBEN VASQUEZ
Specific Plan Cleared 9/2/2021 PEDRO AYALA
Specific Plan Cleared 9/2/2021 PEDRO AYALA
Coastal Zone Cleared 10/7/2021 RUBEN VASQUEZ
Coastal Zone Cleared 10/7/2021 RUBEN VASQUEZ
Frnt yard landscape/Water mgmt Cleared 10/7/2021 RUBEN VASQUEZ
Miscellaneous Cleared 10/7/2021 RUBEN VASQUEZ
Miscellaneous Cleared 10/7/2021 RUBEN VASQUEZ
Specific Plan Cleared 10/7/2021 RUBEN VASQUEZ
ZA Case Cleared 10/7/2021 RUBEN VASQUEZ
Flood clearance Cleared 7/21/2022 BRYAN GATHUKA

Contact Information

Contractor Murphy Frank; Lic. No.: 399420-B P O BOX 1275      VENICE, CA 90291

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 2/7/2024 Partial Inspection HERBERT GIRON
Pre-Inspection 2/21/2024 Partial Inspection HERBERT GIRON
ELECTRICAL-Rough 3/13/2024 Corrections Issued HERBERT GIRON
Insulation 3/13/2024 Approved HERBERT GIRON
Light Gage Steel Frame 3/13/2024 Approved HERBERT GIRON
ELECTRICAL-Final 3/18/2024 Approved HERBERT GIRON
HVAC-Rough 3/18/2024 Approved HERBERT GIRON
BUILDING-Rough-Frame 3/26/2024 Approved HERBERT GIRON
ELECTRICAL-Final 3/26/2024 Corrections Issued HERBERT GIRON
Final 3/26/2024 Corrections Issued HERBERT GIRON
Green Building Final 3/26/2024 Corrections Issued HERBERT GIRON
Green Building Rough 3/26/2024 Approved HERBERT GIRON
HVAC-Final 3/26/2024 Corrections Issued HERBERT GIRON
PLUMBING-Final 3/26/2024 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 3/26/2024 SGSOV Approved HERBERT GIRON
Smoke Detectors 3/26/2024 Approved HERBERT GIRON
Gas Test 4/1/2024 Approved HERBERT GIRON
PLUMBING-Final 4/1/2024 Approved HERBERT GIRON
ELECTRICAL-Final 4/12/2024 Approved HERBERT GIRON
Final 4/12/2024 OK to Issue CofO HERBERT GIRON
Green Building Final 4/12/2024 Approved HERBERT GIRON
HVAC-Final 4/12/2024 Approved HERBERT GIRON